GM answers residents’ questions, concerns regarding proposed capital projects and facility changes
By Jeff MathesonRWC General Manager
In print on pages 10A, 11A and 12A
The following are questions residents submitted during the March 6 Town Hall at the Event Center regarding proposed capital projects and facility changes to Dollar and Gateway Clubhouses.
Q
: Have the financial implications of these proposed capital projects been evaluated, particularly the potential impact on residents’ assessments and the Membership Transfer Fee for prospective buyers?
A
: All capital projects are funded by the RWC Capital Fund. The main source of revenue to the fund comes from Membership Transfer Fees (MTF). The RWC Board authorized an increase to this fee in 2025 with the new fee ($18,000) going into effect April 1, 2026. The fee increases by $1,000 annually thereafter.
The proposed list of projects would be funded by the RWC Capital Fund, as well as from proceeds from the sale of the property owned by RWC at 1220 Rossmoor Parkway. The property is currently in escrow. Sale proceeds will be used to retire the existing three loans secured by the property. These loans were used for the construction of Creekside, the Event Center and the Fitness Center. Once paid, the remaining new proceeds should be around $8 million. A new construction loan will be used for the balance of the project with the principal payments coming from the RWC Capital Fund. Those payments will be lower than the current debt service on the existing three loans that will be retired.
This project will not impact the monthly coupon.
Q
: If the proposed Gateway and Dollar House projects are intended to improve operational efficiency, will residents see any reduction in their monthly coupon or other costs?
A
: Staff are always evaluating services, efficiencies, and all opportunities to control rising costs to the monthly coupon. Those efforts will continue.
Q
: What are the estimated costs of the proposed Gateway and Dollar House renovations compared with renovating or rebuilding the existing offices at 800 Rockview Drive? When will those cost estimates be available?
A
: Developing cost estimates based on final designs is part of the scope of work for ELS. One of the first steps would be the development of the actual plans.
ELS conducted some preliminary studies related to alternatives for replacement of the offices at 800 Rockview. Constructing a new building at the same location was estimated in the $12 million-$15 million range; renovation of the property at 1220 was estimated in the $16 million-$18 million range; and constructing a new building where all site improvements are needed, such as utilities, was $18+ million.
Q
: Has the option of renovating or rebuilding the 800 Rockview Drive offices – including adding an additional floor, demolishing and constructing a multi-story building or using modular or prefabricated structures – been fully evaluated?
A
: Yes.
We evaluated building a two-story building at the same location, options for a prefabricated replacement structure, constructing a new building in the upper RV lot, renovating the building at 1220 Rossmoor Parkway and constructing a new building on the property at 1200 Rossmoor Parkway (former B of A).
Q
: Has the option of leasing administrative office space off campus or in downtown Walnut Creek been considered instead of constructing or remodeling additional office space within Rossmoor?
A
: We have evaluated renovating the building at 1220 Rossmoor Parkway, constructing a new building at 1200 Rossmoor Parkway (former B of A site), as well as a few other local options. No option for property in downtown or other locations has been evaluated.
Q
: Why do staff offices need to be relocated from 800 Rockview Drive, and why is additional administrative office space being proposed elsewhere?
A
: The offices at Rockview serve both administrative and operational functions. The building is a former warehouse that was converted to offices. It is crowded and in poor condition for administrative offices. It has had several floods from storm water as well as sewage back-up. Parking is very poor and access from the employee lot is not to code. As an operational center we have deliveries and work vehicles mixed with resident visitors. Relocating the administrative function so that all RWC/RPM administrative services are together will help with efficiency and service delivery.
Q
: Are there plans to renovate the existing 800 Rockview Drive facilities to improve working space for RPM and accounting staff, and how many staff members would remain at that location?
A
: The operations staff such as foreman, landscape, carpentry, vehicle maintenance, bus operations, would remain at 800 Rockview.
Q
: What alternatives have been evaluated for the Stanley Dollar House, including using it for offices, relocating clubs there or other configurations?
A
: As a site on the National Registry of Historic Places, we want to maintain the character of the Dollar House. Based on the size and configuration, it would not work as administrative offices. The plan is to renovate the house to accommodate club and resident interests as well as a place for informal social gatherings.
Q
: Why is the relocation of the library being proposed when alternatives may exist, such as retaining the current library location or relocating other functions instead?
A
: The scope of work for ELS Architects is to evaluate the overall needs, amenities, services and capacity of Gateway Clubhouse, including parking. Relocating the Library and Computer Center presents a good option for retaining amenities and expanding services. It also allows for a phased approach to the overall project that limits disruption to amenities such as the library, computer center and club functions. As we work toward a final design, we will continue to evaluate options within the Gateway complex.
Q
: How much space is currently used by the Library and Computer Center, and how would those functions fit within the proposed new locations?
A
: The current Library is 2,680 square feet. Of this, 1,280 is for storage, circulation and office space and 1,400 square feet is for functional book and material displays.
The current Computer Center is 420 square feet.
The space at the MPRs as currently conceived would be 2,014 square feet of library space, of which 1,400 square feet would be for functional book and material displays. The Computer Center space would be 575 square feet plus 114 square feet of storage. However, we would not know the actual square footage of the proposed new locations for the library and computer center until space needs are fully assessed and plans are drawn up.
Q
: If the Library and Computer Center are relocated, how long would the current facilities be closed before replacement facilities are available?
A
: The project as currently proposed would be constructed in phases. Phase one would be the Dollar House, phase two the conversion of the MPR’s to a new library and computer center, and phase three renovation of Gateway Buildings B and C. By completing the project in phases, we can limit any downtime. The new Library and Computer Center would be finished and opened before the current sites are closed.
Q
: The current Library, Computer Center and Redwood Room are easily accessible for individuals with disabilities. How will accessibility and ADA compliance be maintained or improved if these facilities are relocated?
A
: Any renovation or new construction must meet current code for accessibility. These codes have become much more stringent over the years. All amenities involved would be accessible. This includes the parking lots and paths of travel.
Q
: Gateway currently serves as a central hub for residents, including the Library, Computer Center, Redwood Room, studios, meeting rooms and covered parking. How will the proposed changes preserve or improve these resident services?
A
: Gateway is a central hub of resident services and activities. The improvements would be specifically planned and designed to maintain and enhance Gateway as a central hub. While the Library and Computer Center may be relocated within the Gateway campus, they will remain a vital component of the services available. Expanded amenities will include a new board meeting room for all Mutual and RWC board meetings, a new food and beverage opportunity and central services available for residents.
Q
: What advantages or tangible benefits will residents receive from the proposed plan?
A
: The project is focused on improving the services and amenities to residents. Any improvements to staffing offices ultimately benefit the residents as the staff provides the majority of services and programs available for residents. The more efficiencies and the more stability we can provide for the staff, the more consistent the delivery of programs and services can become. New amenities such as a new library and Computer Center, new boardroom for Mutual and RWC meetings, new food and beverage opportunities and a fully renovated Dollar House all provide tangible resident benefits.
Residents also would benefit from a centralized desk that could meet all of their needs. We often hear from residents about the inconvenience of driving up the hill to handle questions about coupons and member records and how they are passed from one staff member to another when they have questions. A centralized desk would not be department-specific but instead would handle all resident questions and services in a single location.
Q
: How might these proposed changes affect the marketing of Rossmoor and the perception of prospective buyers who currently see Gateway as a central community amenity?
A
: Gateway will remain a central hub but will be significantly upgraded. Services for residents will be more centralized. A new resident will be able to receive all their information from Member Records, Public Safety, Resales and Alterations and Community Services from one service area. Having the current offices at 800 Rockview as one of the first buildings a new resident sees for Resales is not beneficial.
Q
: Has parking at Gateway and the Dollar House been fully evaluated as part of these proposals, particularly considering increased activity and the needs of an aging community?
A
: An important aspect of the ELS scope of work will be evaluation of parking at both Dollar and Gateway. This includes current code for accessible spaces and paths of travel.
Q
: What provisions are being considered for residents who currently walk to Gateway, such as Waterford residents who may not drive?
A
: Residents will continue to be able to access Gateway by walking. Amenities such as the Library and Computer Center will still be accessible at Gateway. New amenities such as the boardroom, food and beverage opportunities and central services will be available. For any club activities moved to Dollar, residents can access the bus system, which is also scheduled for further evaluation to improve the service in 2026.
Q
: What plans are being developed for clubs and groups currently meeting in the Gateway multipurpose rooms, including the Men’s Exercise Group that has met there for more than 40 years?
A
: Staff and consultants will be conducting some stakeholder group meetings to understand how amenities are currently used and what features need to be included in plans for renovations. Rooms at Dollar House will be available and accessible with a new elevator and improved access.
Q
: How will accessibility and parking needs be addressed for groups that may be displaced from the Gateway multipurpose rooms?
A
: A significant portion of the project is to focus on accessibility for the Dollar House. This includes parking, paths of travel to the house, restrooms and access to the second floor. Clubs that currently meet in the MPRs will have a home at Dollar or another clubhouse. Another aspect of the project is the creation of a new boardroom for mutual and RWC meetings. This will free up meeting room space at other clubhouses.
Q
: Why were residents, clubs and Mutual boards not consulted earlier in the planning process before proposals and studies were initiated?
A
: This is a project that began in 2022 with the adoption of the Facilities Master Plan and in 2025 with the Food and Beverage Study. For each of these, there was significant public input through Town Halls, stakeholder groups, surveys and presentations.
ELS has conducted additional studies related to options for relocating administrative offices. These findings have been presented at the Planning Committee and in the Rossmoor News. The current study requires professional consultants to evaluate what is needed and what is possible within the existing clubhouse amenities. Before a project can be evaluated and discussed publicly, it needs to be developed and studied enough to determine if it is viable. We needed a proposal to be able to present and begin the discussion.
Q
: What level of resident engagement and community input will occur moving forward during the planning and decision-making process?
A
: Staff and the consultants will conduct several stakeholder meetings focused on Dollar and Gateway programs, services and amenities. Additional presentations will be made at the Planning Committee meetings and at other forums. Information will be available through the Rossmoor News regarding the progress of the planning project and opportunities for review and input.
Q
: Will changes to the Facilities Master Plan or the use of major community facilities be presented to residents for a vote or formal input?
A
: Presentations will be planned as well as meetings with stakeholder groups. Decisions will ultimately be made by the RWC Board of Directors following reviews and recommendations from the Planning Committee and the Finance Committee. No public vote regarding the approval of the project is planned.
Q
: Was the consulting contract for the current study competitively bid, and what is the scope of the work being performed?
A
: ELS Architecture has conducted several studies related to the relocation of the offices at 800 Rockview. This has provided them with significant information regarding the staffing needs and operation. ELS has also completed previous projects, so they are very familiar with the community, public outreach and designs. For this project, staff did seek a competitive bid related to the full evaluation and development of design options for just the Dollar House. The proposed scope from ELS for both Dollar House and Gateway was lower. The scope includes evaluation of the existing spaces, evaluation of code compliance, evaluation of parking, initial review with the city, public presentation and stakeholder meetings, all designed to build consensus and present a final plan for consideration by the RWC Board.
Q
: Does the recently approved $157,000 expenditure fund a feasibility study, conceptual planning, or detailed architectural design work?
A
: The scope is for design development, which includes developing cost estimates for the final design option. Preparation of construction plans is the next phase.
Q
: Will the results of the study and related analyses be made publicly available to residents?
A
: Yes, there will be additional presentations as the project evolves.
Q
: How much has Rossmoor spent over the past five years on consulting studies and feasibility analyses related to projects such as the restaurant, pickleball courts, water usage, and other capital planning efforts?
A
: Studies are critical initial steps to the development of capital projects. They are necessary to develop appropriate scopes of work, receive community input and develop key decision points and criteria for consideration. These studies are all funded through the capital budget and are part of each project’s overall budget. Staff reports on the progress and funding for each approved study on a regular basis through the Planning Committee and the Finance Committee. A history of the approved projects including studies is presented annually with consideration of the Capital Budget Priority list. The presentation on the capital program can be found on Simbli: https://tinyurl.com/rwc-capital-priorities
Q
: Why not make greater use of the expertise of Rossmoor residents who may have professional backgrounds relevant to architecture, planning, finance, or engineering?
A
: The RWC Board has a fiduciary duty to rely on advice of licensed professionals. These professionals take on the liability for their advice such as the accuracy of engineering plans. Relying on advice of a volunteer resident does not afford the appropriate protection. Residents also frequently have very specific interests related to projects that may be a conflict of interest.
The Board does encourage resident participation through a variety of means such as focus groups, presentations, input at meetings, etc.
Q
: What analysis supports the projected value of the medical center property if it is sold?
A
: The RWC Board has engaged the services of Colliers International for the marketing and sale of the property at 1220. The property is currently in escrow.
Q
: How will the Board determine whether relocating major amenities – such as the Library – is in the best interest of residents?
A
: Through the design process, the Board will evaluate several factors such as cost, overall program, timing, design elements, parking, etc. Alternatives and an eventual design recommendation are developed with opportunities for public review and input. Presentations will take place as the study evolves. Stakeholder meetings will be conducted for input.
Q
: Why is an elevator being considered for the Stanley Dollar House but not included as part of the Gateway project discussions?
A
: The Dollar House is an existing historic two-story amenity. To improve access to the second floor and expand the usability of the house, an elevator is required. Gateway is currently a single-story building. If a second story were to be considered, an elevator would be required.
Q
: Does the current study include analysis of parking impacts associated with other projects, such as pickleball development and potential activity around the Dollar House and Event Center?
A
: Yes, analysis of available parking in the area as well as any new demand based on the proposed projects will be evaluated.
Q
: Why not consider relocating administrative offices off campus to free up Gateway space for resident activities?
A
: Other locations have been analyzed including relocating to the property at 1220 Rossmoor Parkway, the corner lot at 1200 Rossmoor Parkway, and locations at 800 Rockview. The current proposal creates the greatest benefit for the delivery of programs, services and amenities for the benefit of residents. It is the most feasible, allowing for the scope of work proposed for the Dollar House as well as the improvements at Gateway.
Q
: How is the Board ensuring careful stewardship of resident funds when evaluating large capital expenditures?
A
: The Board carefully evaluates all capital projects on an ongoing basis. This is done through review and recommendations from both the Planning and Finance Committees. Through the development and adoption of the Facilities Master Plan and through the Food and Beverage Studies, the board has evaluated near- and long-term capital needs as well as funding requirements for completion of those projects. These projects are vital to the ongoing success of Rossmoor as an active senior adult community. The proposed projects are possible based on the sale of the property at 1220 Rossmoor Parkway. The proposed project accomplishes a number of priorities identified in the Facilities Master Plan for the most economical cost.
Q
: How will construction quality and oversight be addressed in future projects, particularly given concerns about the quality of recent renovations such as Gateway’s Redwood Room?
A
: Large-scale capital projects involve the use of professional consultants such as ELS Architecture. This ensures the projects meet the design aesthetics and functionality desired by the community for the amenities. Projects such as Creekside, the Event Center and the Fitness Center are examples based on the scope of the proposed project. These projects also go through extensive permitting and regulatory review.
Minor projects have a significantly different standard.
Q
: When will the restaurant open, and what was the final cost of that renovation?
A
: The restaurant will be opening soon. The contract with the new operator includes an allowance of up to $625,000 for improvements. Rossmoor retains all funded improvements.