no entry fees collected to use the pools, and the cost to operate the pools is included in the GRF portion of the monthly coupon at a cost of $12.24/ manor/month.

Facility design and features Q

: Why is an expensive outdoor facility with a roof needed when no other outdoor sports facilities in Rossmoor have roofs? A

: The roof serves two purposes. The main purpose is for sound mitigation and the second is to accommodate solar. Other sports do not produce the same sound as pickleball. Q

: Are rooftop solar panels still part of this project? A

: Yes. Q

: Since the building is not fully enclosed, will courts be playable during the rainy season? A

: Based on the west and south facing walls, the courts should remain playable during most weather conditions. Q

: I’ve heard that two golf holes will be removed due to the new facility, is this true? A

: No, the building will be located in the out of bounds area of the 18th fairway. The golf course will not be impacted. Q

: How will water from roof drains be collected and diverted? A

: Drainage is included in the plan and bio-retention areas are included per city standards. Q

: What’s the foundation design? A

: Foundation to mitigate soil subsidence and drainage plan? The design and construction documents are based on geotechnical reports and soil conditions are taken into consideration along with drainage needs. Q

: Where can we review the design reports? A

: The general design has been shared and posted on Rossmoor.com. Specific construction plans are still a work in progress and not available. Q

: Can the GRF Board look into an air dome rather than a regular building structure of metal and wood? A

: An air dome is more of a temporary-type structure and would need to be replaced long before the proposed permanent steel structure. We also want the aesthetics to be fitting of the area and Rossmoor in general. Q

: If this facility moves forward, will it be a multipurpose room facility? A

: The facility is designed for pickleball, and the primary use is

intended to be pickleball. Q

: Is ELS Architecture & Urban Design a “design and build” firm? A

: No, they are not general contractors.

Financial concerns Q

: Will GRF be taking out additional loans to pay for this facility? A

: No loans are planned for this project. Q

: What is the backup plan to finance the project if the projected 2025 transfer fees fall short? A

: The Trust Estate Fund has a reserve of $3.75 million. Not all budgeted projects begin at the same time. Should sales come in slower than estimated, the Board would need to consider options related to the timing of projects. Q

: We are paying $1.9 million dollars in debt service annually. Why not pay down those loans? A

: There are three outstanding loans. The first matures in 2027. These were all 15-year loans at favorable interest rates. The Board could pay them off more quickly, but this would limit the ability to complete other priority projects. Q

: Why $4 million for 700 people? Why not use the money to lower the coupon? A

: The Trust Estate Fund cannot be used for operating expenses. Per the Trust Agreement, operating expenses must come from the carrying charges (coupon). This project will serve the community for many years to come, not just the current members of the Pickleball Club. Q

: Will the operating expenses have an effect on the coupon? A

: The projected operating expenses including property taxes, custodial, maintenance, and landscaping are estimated to be $60,000 annually. This equals $0.75/manor/month. Q

: What are the itemized costs that make up the annual $60,000 estimated to operate and maintain the new pickleball facility? A

: These costs include property taxes ($30,000 to $40,000), custodial

supplies to clean and empty trash, landscape plan materials and irrigation supplies and tech time, annual fire inspection for the suppression system, and minor maintenance. Q

: What are the limitations/uses of the GRF Trust Fund? The Trust Fund is for capital projects and equipment on Trust property. It cannot be used for operating expenses or on Mutual property. Q

: Why is the cost $4 million and counting? A

: The cost is based on a pre-construction bid. Once permits are secured, we will receive competitive bids to determine the actual construction phase budget. The cost per square foot is in line with other commercial buildings factoring out plumbing and HVAC systems. Q

: Do the cost estimates account for an increase in price materials and labor after the latest SoCal fires? A

: We will not know the final construction costs until the project is put out to competitive bid. At that time, we will know if the LA fires or other economic conditions influence cost estimates. Q

: If Transfer Fund fees are insufficient at some point to pay the principal and interest on the multi-million debt that is proposed, how will the shortfall be addressed? A

: No new debt is planned for this project. The Trust Estate Fund has sufficient balance to pay the loan payments for 2025. Q

: How quickly will $4 million be recovered by home sales? A

: The current Membership Transfer Fee is $13,500, and we are projecting 400 sales in 2025. Q

: How will we be able to pay for pickleball and a new MOD building? A

: The MOD replacement is being studied. There are a few options that involve the remodel or sale of the Medical Center property. This project also intersects admin space at Gateway and future space for member amenities, which may include additional food and beverage options. It is too early in the evaluation process to deter-

mine cost and funding. Q

: Is there any final cost of the pickleball courts beyond what the GRF will reconsider with this project? A

: Once competitive bids are received, a final construction phase budget will be prepared. If the costs exceed current estimates, the GRF Board will need to determine appropriate next steps. Q

: Why doesn’t the Pickleball Club donate $500,000 to the project to show that they are really interested? A

: No club or group of residents has ever been asked to fund a major capital project that will serve the community well into the future. Clubs have donated items or shared in the cost of minor improvements based on specific club interests. For example, the Performing Arts Guild contributed funds for risers and stage lighting in Las Trampas and the Tennis Club purchased the shed at Buckeye. These contributions were important, but minor in terms of overall construction costs of a major project. Q

: What was the proposed cost of the facility when the initial approval was obtained? A

: The original plan was to resurface the courts at Creekside and expand the footprint to accommodate seven courts. The cost estimate was $300,000. Once studies were done on soil conditions and the erosion of the creek, the project costs escalated quickly and permits for this location became questionable based on the proximity to the creek. Q

: With no firm design or bid, construction costs continuing to escalate, especially after the LA fires, is there any chance that the current $4 million estimate will hold? A

: The estimate is based on a contractor bid. Once permits are secured we will seek competitive bids. Economic conditions may influence the final best bid and be higher or lower. Q

: Why do we need another court for a lot of money when there are courts in Lafayette, Rudgear, Orinda, etc.? A

: The same could be said about all Rossmoor amenities. There are fitness centers, golf courses, pools, meeting halls, performing arts venues, tennis courts, bocce courts, etc. outside the gate. The desire for most residents is to have services and facilities readily available, that are inside the gate and controlled by Rossmoor. Q

: Why is so much money being spent for an issue that is contested and controversial? A

: Most issues in Rossmoor are contested, and input is con-

sidered in the process. The Event Center is a crown jewel of Rossmoor. It was the most controversial project faced by this community. To the credit of the Board at the time, they did not let controversy detract them from accomplishing the project. Q

: With $3 million already set aside, what can we build for that Event Center that will not require additional funds? A

: Once the project is put out to bid, we will know the final cost. The capital budget includes funds based on an estimate of $4 million. The proposed pickleball facility has been identified in the Facilities Master Plan.

Operational questions Q

: Will the facility be open to non-pickleball club members? A

: Once constructed, the Policy Committee and the GRF Board will adopt rules governing the use of the facility. Time will be designated for non-club members to enjoy playing on the courts. Q

: What is the schedule for the bid process? A

: We anticipate securing permits by March and begin the bid process, which may take 6 to 8 weeks. Q

: Will GRF select the lowest bid? A

: The GRF Board is not required to select the lowest bid. They may select the most responsive bidder that demonstrates a strong track record of completing projects on time and within budget. Q

: What will the hours of play be? A

: The hours will be 8 a.m. to 6 p.m. daily. Q

: Will parking be a problem if other events are going on? A

: Parking will be managed. Q

: Will music be allowed? A

: This will be evaluated as part of the facility rules. Q

: Will soft paddles be required? A

: Green paddles will be required but not soft paddles. This changes the nature of the game. Q

: Once the facility is built, will Creekside courts and Fitness Center Gym still be available? A

: Yes. Q

: What’s the plan for Creekside courts?

Q&A: Answering questions about facility design, financial concerns

Continued from page 20A

News photo by Dan Rosenstrauch A large crowd filled the Event Center for the Pickleball Town Hall last week.

Continued on page 22A