Work on Del Valle pools stalled due to new building permit requirements
By Maggie SharpeStaff writer

Work on the swimming pools at Del Valle has stalled. Instead of the anticipated July 1 reopening date for the two pools and sauna, Director of Resident Services Jeff Matheson projects that the facilities will reopen sometime in August – but that’s not set in stone.
“We hope to submit a revised set of plans to the city of Walnut Creek as soon as possible so that work can get back underway with the goal of reopening sometime in August,” said Matheson.
Revised plans are needed because the project ran into unforeseen problems when the city said the project needed building permits in addition to the county’s health permits that GRF has already secured.
Since GRF considered work on the pools to be routine maintenance, rather than renovation, it was not expected that building permits would be required.
“This is not something we anticipated. We approached this as maintenance because plastering, pumps and heaters have to be replaced on a pool every few years,” said Matheson. “From our standpoint, this was maintenance, rather than renovation.”
Access issues
Since the Fitness Center is not scheduled to reopen until January 2018, and is blocked off during construction, temporary access to the pools is needed. GRF’s plan to create temporary access to the pools through the patio (located between pools and parking lot) triggered the city’s decision to reassess access to the pools, specifically for people with disabilities.
“As the pool project is associated with the other (Fitness Center) project, the city needs to check access, especially since the temporary access is through the patio,” said Matheson.
He said Walnut Creek has a construction valuation threshold of $150,000 for determining how much of the building needs to be brought up to current accessibility code.
Currently, the pools are accessible from the patio via three steps down from the parking lot or there is also a flat path.
There are two doors to negotiate: one security-type double door from the steps and path to the patio, and another single door from the patio to the pools.
The next step is a review of the facility by an access specialist to determine what items need to be brought into compliance.
These items include such things as lifts, pool deck, hand rails, steps, signage, doors and door handles.
Cost of work
The original cost of work on the Del Valle pools and sauna was $466,500, which was approved by the GRF Board earlier this year.
That included $165,000 for the plaster job and $182,500 for replacing heaters and pumps.
A new addition of an ultraviolet sanitation system to remove contaminants and improve indoor air quality came in at a cost of $120,000.
An accessible unisex changing room with shower and toilet, located off the pool deck, is also planned.
Any additional work that results from the city’s assessment will doubtless affect the project budget, but the dollar figure is yet to be determined.
“Currently we are evaluating what additional work will need to be included in the project to bring the facility into compliance with current building code with respect to accessibility,” said Matheson. “Once this is complete we will have a better idea of the impact on the project budget.”
Residents’ reactions
Matheson said there was a “significant outcry” from residents when the pool closures were first announced.
But the outcry has since subsided, since swimmers still have access to the same classes at Dollar and Hillside pools – there have been just minor adjustments for lap swimming and bee issues.
“All in all, people have adapted well and have been very patient – which we appreciate,” said Matheson, adding that both Dollar and Hillside pools are up to speed on maintenance.
Matheson said that once they get clearance from the city to complete the work on Del Valle – so far, just the plaster and tile have been removed – it is anticipated that the work will take three or four weeks to complete.
All the components for the project, such as heaters and pumps, are already on site, just waiting for the city’s green light before they can be installed.
And the good news, said Matheson, is that the Fitness Center renovation is right on track.
“We’re looking at furnishing the facility in December and having an early January opening,” he said.
Meanwhile, residents can continue to enjoy exercise classes in the three Modulars located in the Del Valle parking lot.