Timetable announced for Fitness Center renovation – construction starts soon
By Cathy TallynStaff writer

With the approval of a $8.4 million budget for the renovation of the Del Valle Fitness Center, the GRF Board has set in motion a 10-month construction schedule.
The Fitness Center will be gutted and rebuilt to better serve residents. The timetable has demolition and construction getting underway in late March with the Fitness Center reopening in early January 2018. Four modular buildings will be put in the Del Valle parking lot to house some fitness programs and classes. That means 40 parking spaces will be lost. Other classes will be offered at Rossmoor’s other clubhouses, but may be on different days and times.
Because the work will be done all at once in order to save money, residents will be unable to work out for three weeks, beginning Monday, March 13. “Efforts are being made so that there will be only three weeks that residents can’t work out,” said Jeff Matheson, director of Resident Services..
That allows time to install the portable buildings and pack up and move the equipment into the temporary quarters.
It’s anticipated that the Del Valle swimming pools will be open most of the time during construction. There will be restrooms in the portables, but there will be no locker rooms.
“It will take some sacrifices on the part of everyone, but the end result will be worth it,” said Matheson.
There will be more usable space so there is less crowding. There will also be new equipment and furnishings. The inside of the new Fitness Center will be more light and airy.
Rossmoor will need to get permits from the city of Walnut Creek before the work can begin.
“We anticipate closing the Fitness Center on March 13. Once it’s closed, we’ll pack up everything in the facility,” Matheson said. “Absolutely everything needs to be moved out.”
The equipment will be moved into the portables or put in storage. The temporary buildings are scheduled to open Monday, April 3.
Relocating
The largest of the temporary buildings, call modular, will house fitness equipment. Another large building will be devoted to aerobics and other classes. There will be restrooms in another building. And, administration will be in a fourth building.
There will be the same level of programs as there is now, Matheson said.
A challenge is to relocate some 40 classes offered each week. They will be held in the portables and in other clubhouses.
“A schedule of classes will be available very soon.” Matheson said. “As far as the pools go, we’re trying to keep them open as much as possible. There will definitely be times when they need to be closed.”
Present plans don’t call for locker rooms. The hope is that residents will come to the pools in their swimsuits and wait to shower and change until they get home. The Hillside and Dollar pools will be open during construction at Del Valle.
It’s not anticipated that there will be parking problems at Del Valle because fewer classes will be held there, he said.
The GRF Board voted Feb. 14 to approve a Fitness Center renovation budget of $9.6 million as well as hire Tilton Pacific Contractors and approve renting of modular buildings.
The total construction phase budget is $8.4 million with another $1.1 million in costs previously authorized. The construction bid is $6.2 million. The temporary buildings and services that go along with those buildings will cost $310,000. Fixtures, furnishings and equipment budget is $851,000. The money will come from the Trust Estate Fund. Money in that fund comes from the $9,000 Membership Transfer Fee paid by new residents.
A list of classes along with dates, locations and meeting times will be available soon online at www.rossmoorfitness. Residents will also be able to get updates on the renovation. The website is currently under construction.