14A Rossmoor News • February 22, 2017 GRF Board News Board approves Fitness Center renovation budget and contractor
Continued from page 1A
Modular building will be in Del Valle parking lot during construction
Continued from page 1A
The rendering shows the locations of the temporary modular buildings that will be set up in the Del Valle parking lot during the Fitness Center renovation. The large building on the left is the main fitness center; the next building is for administrative staff; the third building is for restrooms; and the last building on the right is for stretching and aerobics.
GRF Director Steve Roath had several questions about the Fitness Center renovation project during last Tuesday’s mid-month meeting.
News photos by Mike DiCarlo GRF Director Ken Haley and President Les Birdsall listen to a presentation on the Fitness Center.
Two union representatives stood outside the Rossmoor gate last week protesting Golden Rain Foundation’s decision to hire a contractor for the Fitness Center that does not hire union labor. ArcPath, listed on the sign on the left, is the company that is handling the project management of the Fitness Center renovation.
nut Creek before the work can begin.
“We anticipate closing the Fitness Center on March 13. Once it’s closed, we’ll pack up everything in the facility,” Matheson said. “Absolutely everything needs to be moved out.”
The equipment will be moved into the portables or put in storage. The temporary buildings are scheduled to open Monday, April 3.
Relocating The largest of the temporary buildings, call modular, will house fitness equipment. Another large building will be devoted to aerobics and other classes. There will be restrooms in another building. And, administration will be in a fourth building.
There will be the same level of programs as there is now, Matheson said.
A challenge is to relocate some 40 classes offered each week. They will be held in the portables and in other clubhouses.
“A schedule of classes will be available very soon.” Matheson said. “As far as the pools go, we’re trying to keep them open
as much as possible. There will definitely be times when they need to be closed.”
Present plans don’t call for locker rooms. The hope is that residents will come to the pools in their swimsuits and wait to shower and change until they get home. The Hillside and Dollar pools will be open during construction at Del Valle.
It’s not anticipated that there will be parking problems at Del Valle because fewer classes will be held there, he said.
The GRF Board voted Feb. 14 to approve a Fitness Center renovation budget of $9.6 million as well as hire Tilton Pacific Contractors and approve renting of modular buildings.
The total construction phase budget is $8.4 million with another $1.1 million in costs previously authorized. The construction bid is $6.2 million. The temporary buildings and services that go along with those buildings will cost $310,000. Fixtures, furnishings and equipment budget is $851,000. The money will come from the Trust Estate Fund. Money in that fund comes from the $9,000 Membership Transfer Fee paid by
new residents.
A list of classes along with dates, locations and meeting
times will be available soon online at www.rossmoorfitness. Residents will also be able to get
updates on the renovation. The website is currently under construction.
Urban Design in January 2016. The project manager, Fred Ponce from ArcPath Project Delivery, was hired last March.
Matheson said he was pleased to announce that the renovated Fitness Center will be completed within the Board’s budget. “When this amount is combined with previously authorized funding, it brings the project total all-in budget to $9,616,300,” he said.
Bidding process Matheson explained that the project went out for competitive bid back in October. The companies were selected based on their specific experience with fitness center and community center projects. Out of the three bids, two were relatively close while a third was substantially low.
“Having one bid lower raised some concerns about the accuracy of the bid,” he said. “Staff and our project manager discussed the bids with each of the companies and feel confident that the bid proposed by Tilton Pacific more accurately reflects the true cost of the project.”
Matheson said that Tilton Pacific displayed a thorough understanding of the project. “Tilton submitted detailed questions during the bidding process and they had a good response from subs to most trades and seemed more confident in their bid,” he said.
The modular Four modular units will be set up in the center of the Del Valle parking lot (see accompanying story for more details).
The plan is to have the buildings delivered later in March. The Fitness Center will need to be closed for a few weeks to get ready for the move. Once the modular buildings are set up, the Fitness Center will reopen in the temporary facilities.
Matheson explained that the agreement with Mobil Modular is for $178,128, but that the total cost for temporary facilities is $310,000. “This amount includes moving costs, temporary power and Comcast cabling, storage fees and a temporary shower building for the pools,” he said.
Board concerns Director Mary Lou Delpech asked Matheson if he expected problems with the union since the approved contractor will not always use union workers. He explained that just when the Event Center was under construction, union representatives will be outside the gate protesting for a while.
Director Geri Pyle was concerned that there would not be enough parking with the modular units taking up so much space in the middle of the lot.
Matheson explained that a number of activities that take place now at the Fitness Center will be moved to other locations and that will significantly free up some parking spaces. For example, pickleball will be played on the courts on Rossmoor Parkway and many of the classes will move to Hillside and other venues.
Director Steve Roath wondered if there would be savings in the Fitness Center operations
during the renovation. Matheson said that staffing levels will remain the same and there will still be costs associated with electricity, so savings would be limited.
President says thanks After the Board approvals of all the motions related to the Fitness Center renovation, President Les Birdsall thanked all those involved in getting it to this point.
“Thank you to all residents, Fitness and Aquatics Committees, Fitness Supervisor Masha Henzel and all the staff who contributed along the way in this process,” he said. “Thanks to CFO Rick Chakoff and the Finance Committee for making sure we can afford the project. Thanks to CEO Tim O’Keefe who stepped in during the process. He caught up very quickly.”
He gave a special thanks to Matheson who has been guid-
ing the project every step of the way. “I’m sure there have been many times when he wished he could give it to someone else. I am so happy he didn’t,” said Birdsall. “We could not be this far along without him. I thank you, the Board thanks you and
Rossmoor thanks you.”
He also thanked the members of the GRF Board for their “commitment, thoughtfulness, careful analysis and ability to work as a team.”
“I’m happy and proud to be part of this team,” he said.
Photos on this page
- Ken Haley and Les Birdsall sit at a dais with microphones and listen to a presentation. Caption: GRF Director Ken Haley and President Les Birdsall listen to a presentation on the Fitness Center.
- Steve Roath, a GRF director, sits at a table with a microphone and gestures while speaking. Caption: GRF Director Steve Roath had several questions about the Fitness Center renovation project during last Tuesday’s mid-month meeting.
- Two union protest signs reading Labor Dispute stand near the Rossmoor gate, with people standing beside them. Caption: Two union representatives stood outside the Rossmoor gate last week protesting Golden Rain Foundation’s decision to hire a contractor for the Fitness Center that does not hire union labor. ArcPath, listed on the sign on the left, is the company that is handling the project management of the Fitness Center renovation.
- Site plan drawing showing the temporary modular buildings placed in the Del Valle parking lot for the Fitness Center renovation. Caption: The rendering shows the locations of the temporary modular buildings that will be set up in the Del Valle parking lot during the Fitness Center renovation. The large building on the left is the main fitness center; the next building is for administrative staff; the third building is for restrooms; and the last building on the right is for stretching and aerobics.