PG&E installing temporary structures in Rossmoor
In print on page 2A

ect since January. The work includes replacing a 27-milelong, 230-kilovolt transmission power line that connects the Contra Costa Power Plant Substation in Antioch to the Moraga Substation in Orinda. The project is in Rossmoor because the community is near the transmission line that is scheduled for improvements.
The scope of PG&E’s work in Rossmoor includes gravel and fabric placement on roads, a helicopter landing zone and pull site; clearing brush as needed; weed abatement; minor tree trimming; installation of temporary fencing as needed; and installation of a temporary security gate.
For information on the project, contact Customer Outreach Specialist Denise Conway at 877-207-1245 during business hours or email ContraCostaMoraga@pge.com.