PG&E crew installing temporary structures on Rossmoor streets for power line upgrade

In print on page 1A

A helicopter hangs from a cable near a tall steel power tower on a grassy hillside under a blue sky.
PG&E brought a helicopter in last week to do work on a tower on Shadowhawk Way.Photo by Karen Brandreth

PG&E was in Rossmoor last week extending the cage tops on towers near Ptarmigan Drive and Shadowhawk Way via helicopter as part of its 2015 power-line upgrade project.

In addition, a PG&E crew installed temporary guard structures on Terra Granada Drive, Ptarmigan Drive, Rossmoor Parkway, Tice Creek Drive and Saklan Indian Drive that will be up during the duration of the project. The areas where these structures have been installed will be restored when the project is completed.

Site preparation work will continue through August and the wire pulling work is not expected to begin until late September or early October. Restoration will follow the pulling.

PG&E has been working on a power line upgrade proj-