Planning Committee gets update on Rockview office upgrade
Further study requested for Creekside courts
By Sam RichardsStaff writer

Saying that decisions about the future of the 800 Rockview office building should wait until an analysis of the full Dollar-Gateway-Rockview project is complete, members of the Rossmoor Walnut Creek Planning Committee on Thursday stood pat on making any such decision, after hearing about several options for refurbishing or rebuilding the offices at the top of the hill.
The RWC Board voted in February to pay ELS Architecture and Urban Design, based in Berkeley, to study a wide-ranging concept to move most RWC and Rossmoor Property Management functions now at Rockview into a significantly remodeled Gateway clubhouse and administration building. Under the original concept, some functions now at Gateway would have moved to a refurbished Dollar House, while others would have relocated within Gateway.
That plan, which would have substantially remodeled Gateway to accommodate many staffers now based at Rockview, drew significant pushback from residents who didn’t want Gateway ‒ especially the Library housed there ‒ to be drastically changed. That sentiment prompted the RWC Board in June to approve concentrating current efforts on further study of refurbishing or rebuilding the RWC and RPM office building at Rockview to improve conditions for employees based there.
On Thursday, the Planning Committee received rough cost estimates for each of three options for improving facilities at Rockview, evaluated and priced based on architectural, structural, mechanical, electrical and plumbing work envisioned. The cost estimates include contingencies and other support costs. Those options are:
• No. 1 – Remodeling the existing main building, preserving its shell and primary structural framing where feasible. Estimated cost: $9.1 million.
• No. 2 – New from-theground-up single-story construction of a main building, approximately the same size on the existing site. Estimated cost: $11 million.
• No. 3 – Replacement of the existing main building with prefabricated modular building units on a new foundation. Estimated cost: $10 million.
David Masenten of ELS told the committee he was surprised the remodel/renovate option was almost as expensive as new construction or building modules would be, given cost saving was the main reason that option was analyzed. “You can renovate it – at a significant cost,” but it’s possible, he said.
Masenten said renovation, modular buildings and new construction “are all reasonable options, but costly options.”
Modular buildings, he said, are generally 12-by-60 feet each and are highly customizable. They aren’t much cheaper than new construction, he said, but could be ready in three to four months, significantly less time than ground-up construction. And though often seen as a “temporary” solution, modular buildings typically last at least 30 years, as opposed to 50 years for new construction, Masenten said.

During the meeting’s Members Forum, resident Carol Weed told the committee she saw a presentation earlier this year hosted by the Chinese American Association of Rossmoor in which an architect’s proposal for a similar scope of construction at Rockview could be done for between $1 million and $2 million. Committee member Leanne Hamaji asked Masenten for his thoughts on that proposal as described by Weed; Masenten called it “unrealistic given today’s construction climate.”
RWC General Manager Jeff Matheson suggested no formal action be taken on choosing one of the aforementioned three options until specific possibilities for the Gateway Complex and for Dollar House have been more thoroughly researched. An eatery at Gateway and additional meeting spaces with an elevator at Dollar remain possibilities for those clubhouses. A detailed analysis for those clubhouses, similar to the treatment given Rockview, could happen by the end of the year, Matheson said.
“We need to have a plan for all these sites before the Board can make informed decisions,” Matheson said. No formal action was taken.
Creekside pickleball courts
The Planning Committee voted on Thursday to ask RWC staff to create a more detailed evaluation of the future of the Creekside pickleball courts, including more options for what to do with that land, after the new building near the Event Center and Dollar opens, now expected at the end of August. Consultants could be hired to supplement staff’s efforts if needed, committee members said.
In June, the Planning Committee recommended the Creekside Courts be closed two weeks after the new pickleball facility opens and that the Creekside courts remain closed while a study evaluates whether they can be, or should be, repaired and reopened. The Board formally requested this action at its July 30 meeting, and sent the matter back to the Planning Committee for more discussion and more study.
Two residents on Thursday offered comments about the courts’ future ‒ one suggested the area be turned into an Americans With Disabilities Act-compliant park; the other lobbied for giving it over to nature. Committee member Nan Warren said badminton courts may be a good fit there. A more thorough report by staff, or possibly by a consultant, will be needed “to evaluate whatever happens on those courts,” Hamaji said.
Committee member Adrian Byram said he favored “taking a pause” to carefully consider all the options, including some not discussed before. “We need to step back and take a new look and not be held back by what’s been studied before … We haven’t really explored what the options are because we’ve been trapped by what we’ve done in the past,” he said.
The other three committee members agreed they want more options to consider, but favored moving ahead with that sooner rather than later, and with new geotechnical and acoustic studies, hopefully for the committee’s September meeting Sept. 10. The vote was 3-0, with Byram abstaining. Rossmoor paving Also on Thursday, the Planning Committee authorized spending about $685,000 from the RWC Capital Budget for “full-depth paving replacement” on Lower Golden Rain Road between Golden Rain Road and Pine Knoll Drive; Oakmont Drive between Tice Creek Drive and Rockledge Lane; all of Canyonwood Court; and Terra Granada Drive between Ptarmigan Drive and Avenida Sevilla. The committee also voted to spend an additional $165,000 from the RWC Facility and Maintenance Budget for surface-level paving for Leisure Lane and the Hillside Pool parking lot.