Rossmoor News, May 20, 2026

Details emerge on three options for major Rossmoor renovations

By Sam RichardsStaff writer

In print on pages 1A, 14A and 15A

A modern carport-covered fuel pump area sits beside a long, low, pale green office building on a sunny day.
The Property Management staff office building sits across from a fuel pump in the corporation yard on Rockview Drive.News photo by Javier Roman

More specific details about initial options for renovation of Rossmoor facilities at Gateway, at 800 Rockview Drive and the Dollar House were presented Thursday at the monthly Planning Committee meeting, ahead of today’s Open House at the Event Center to gather specific written feedback about those three proposed options.

About 50 people came to the Planning Committee meeting, which was moved from the Gateway Board Room to Creekside’s Fairway Room to accommodate the larger crowd. Those people came to hear more specifics about the three current options. As laid out to the Planning Committee on Thursday, they are:

1. Moving the Rossmoor Walnut Creek (RWC) and Rossmoor Property Management (RPM) staff now based at the top of Rockview Drive (800 Rockview) into a new building where the existing one now stands. The current building has had major plumbing failures in the recent past; any renovation or replacement would require all plumbing, electrical and mechanical systems to be brought up to code, Matheson said. This option also could include a “Fireside Café” in the ante room of the Fireside Room, with the Multipurpose Rooms remade into a board room and meeting center. It wouldn’t include a second story, which is considered prohibitively expensive. The Library would remain at Gateway.

2. The original scenario that was the subject of a March 6 Town Hall meeting at the Event Center, and that has generated significant discussion over the past few months. This would have most RWC and RPM functions now at Rockview moving into a significantly remodeled Gateway clubhouse and administration building. The open space between those two buildings would be filled in, and the Library and Computer Center would be moved from their spaces at Gateway Clubhouse into a remodeled Multipurpose Room building at Gateway. Clubs and other groups that now meet in the MPRs, Matheson said, would meet in a renovated Dollar Clubhouse. Dollar’s renovation could include a café there. This option would also include 34 new parking spaces at Gateway, mostly created by changing parking spaces from slanted to 90-degree parking spaces.

3. Described as the “community hub” model, leaving the Library and Computer Center in Gateway Clubhouse (although the Computer Center would move a short distance), adding food and beverage service to the clubhouse, moving the Board Room to the remodeled MPRs, and bringing Rockview staff to Gateway (including the area between the clubhouse and admin buildings that would be enclosed). Clubs and other groups that now meet in the MPRs would meet in the renovated Dollar House.

All three options provide for sorely needed renovations at Dollar, including updated restrooms, a café and an elevator to improve access to the second floor, where new meeting rooms would be created from old, underused spaces. Also, 57 parking spaces would be created at Dollar, bringing the total to 235. All three options also include adding some form of food and beverage service to Gateway, either indoors or in an outdoor court area between the two existing buildings, depending on the improvements eventually approved.

All three also envision a new meeting center shared by the Mutual and RWC boards in a council-style chamber, moving the Mutuals out of the clubhouses, and potentially freeing up about 450 rooms a year for club and private rentals.

None of the three options would leave the Redwood Room intact. Matheson said part of the plan for Dollar House renovation is to create social gathering spaces there that would take the place of the current Redwood Room.

The overall target project budget is $16 million to $18 million. Approximately $8 million would come from the sale of the former John Muir medical building at 1220 Rossmoor Parkway, and another $8 million or so would be financed, Matheson said.

Those three options emerged after other alternatives had been evaluated and rejected over the past few years. They included replacing the building at 800 Rockview with a new two-story structure (too expensive); a new RPM building elsewhere at Rockview (too expensive, access issues using an East Bay Municipal Utility District-owned road); turning the former John Muir medical building at 1220 Rossmoor Parkway into a consolidated administration hub (building proved unsuitable, finances); and buying the vacant former Bank of America building at the corner of Tice Valley and Rossmoor Parkway (building came off the market).

Once a preferred option is developed ‒ likely something somewhat different from any of the three options laid out on Thursday ‒ ELS’s design team will start working with individual groups on specific wants and needs for each space.

Twelve people spoke during Members Forum time at this meeting. Comments included a plea to refurbish 800 Rockview as minimally, and sustainably, as possible; fears that concentrating employees at Gateway would adversely affect parking and traffic congestion there; a plea to preserve, if possible, the Dollar House’s catering kitchen; and even razing Dollar House and replacing it with an “office tower and underground parking.”

Planning Committee members and audience seated in a meeting room, with David Masenten of ELS Architecture speaking at a table with microphones and laptops.
David Masenten of ELS Architecture discusses the Dollar/Gateway/Rockview project during last week’s Planning Committee meeting in the Fairway Room.News photo by Javier Roman

At the Open House today, these three options will be presented again to three groups of 100 pre-registered participants each over three separate halfhour sessions (or more sessions if demand warrants). Visitors will tour displays of each option and ask questions, rank options, and provide written feedback. Based on that feedback, a second event will be scheduled to review what input was received and how the input can or cannot be addressed within each option. Refinements will be prepared for review and input. This process will continue until the RWC Board has enough information to consider approving a preferred design option. It’s a process, Matheson said earlier, that could take a few years before physical remodeling and construction begin.

The current options that are being reviewed can be seen in more detail at https://tinyurl.com/clubhouse-project Transit study consultant contract Also on Thursday, the Planning Committee voted 4-0 to recommend that the RWC Board hire Fehr & Peers, a Walnut Creek-based civil engineering company, for work on an update of Rossmoor’s ShortRange Transit Plan, which would involve a comprehensive evaluation of Rossmoor’s existing transit system, resident surveys of what services they want, and analysis of what is practical and possible.

The work Fehr & Peers would be expected to do includes a full analysis of Rossmoor’s existing transit operation, including Dial-A-Bus, paratransit and subsidized ride-share services; evaluation of ridership trends, including post-pandemic usage patterns, service demand and changes in travel behavior; and outreach to determine current and future demand for transit services to and from key points, including within Rossmoor and to downtown Walnut Creek/BART, the Rossmoor Shopping Center and various medical facilities.

Fehr & Peers, one of two companies that submitted proposals for this update, completed the most recent update of the Short-Range Transit Plan, in 2018. That familiarity with Rossmoor’s existing transportation system and its structure and operational conditions, committee member Adrian Byram said, should help the firm build upon its earlier work in Rossmoor.

The firm’s work would include onboard surveys, community workshops and other targeted outreach methods to gather input on service performance, travel patterns and future demand.

The contract would be for up to $80,000, paid from RWC’s capital fund. Planning Committee member Leanne Hamaji said that if the RWC Board approves this contract this month, the study results could come to the full Board early in 2027.

Stanley Dollar Drive

gate security The Planning Committee also voted Thursday to recommend to the full Board to spend almost $28,000 for fencing and security cameras for the perimeter gate at the top of Stanley Dollar Drive, and an agreement with Securitas for “remote system monitoring” of that gate into Rossmoor.

Though few trespassers have entered Rossmoor through this gate over the past 30 years, the recent removal of a secondary gate down the hill on the Lafayette side has made that Rossmoor entry point more accessible. Tom Cashion, Rossmoor’s director of public safety, said that, since that secondary gate’s removal, Rossmoor has experienced a “notable increase in security incidents” believed to have originated from this access point.

“People who are not authorized to be in Rossmoor have committed crimes in Rossmoor,” he said.

Operating and maintaining the camera system would cost $3,690.72 annually, to be paid from RWC’s operating budget, for each of the first three years the cameras are in place.