Planning Committee supports golf bridge work, Ceramic Arts Club mural
By Sam RichardsStaff writer

Rossmoor Walnut Creek’s Planning Committee on Thursday voted to recommend that the RWC Board authorize moving to the next phase of the project to replace two golf cart bridges on the Creekside course spanning Tice Creek.
The committee’s recommendation calls for up to $122,132 to be allotted to BKF Civil Engineers for Phase II of work on the golf bridge replacement capital project. The money will come from the RWC capital budget.
In January 2023, replacing these two golf course bridges – one adjacent to the Hole 5 fairway and the other near Hole 7 and the Hole 7 tee boxes – was among the “Priority 1” capital projects approved by the Board, part of a larger plan to replace most or all these bridges by the end of 2033.
Phase I of the overall study by BKF Civil Engineers ‒ geotechnical investigation and analysis and a hydrology study, preliminary bridge designs with a consulting structural engineer and other prep work ‒ is complete, according to committee documents. BKF is now ready to proceed with the second phase of work including producing construction documents and nailing down designs, RWC Director of Community Services Ann Mottola told the committee. The bridges will have concrete pathways (as opposed to wood), she added.
The project will replace the existing Tice Creek crossings with new bridges that will span the creek longer and higher than the existing ones to minimize the bridges’ impact on the creekside geology. Additional improvements and restoration will occur in the creek to armor the bridge abutments.
The RWC Board first approved money for golf bridge replacement as part of the 2023 capital budget. The hope is to replace most or all of these bridges by the end of 2033.
CAC mural project Also on Thursday, the Planning Committee endorsed the site plan and artwork design for a mural that would be installed by the Ceramic Arts Club adjacent to the totem pole art pieces behind the club studios at Gateway. It voted to recommend that the RWC Board do the same.
The Planning Committee was given its first look at the mural project in November, when the Ceramic Arts Club did a presentation on it. The site for the artwork was approved by the RWC Board at its Dec. 4 meeting, and the Board will ultimately have to approve the overall project.
The CAC has enlisted help from several notable artists familiar with public art installations to assist with the mural project.
As currently proposed, the mural would stretch over four 5-by-5-foot removable panels, with the mural itself 18 inches above the ground. There is also an accompanying landscaping plan to go with it.
Linda Mariano, a CAC vice president, said the four panels, taken as one work, will depict the nature in which Rossmoor sits, from the hills to the various animals (turkeys, deer, coyote, egrets, a raccoon and others) that call the Rossmoor area home, as well as a couple on a bench. The four panels are meant to be viewed from left to right, Mariano said, moving viewers through both the times of the day and the seasons of the year.

“The only thing I see missing is a bobcat,” said Dwight Walker, who was serving at his last committee meeting before moving from the area.
Fitness Center skylight The committee on Thursday also voted unanimously to recommend that the RWC Board spend up to $28,360 to replace the skylights at Tice Creek Fitness Center. The existing skylights are well beyond their estimated 20-year lifespan, and if not replaced could cause leaks into the center.
The project has been on the RWC capital projects list since 2024. Flynn Architecture, which has done other work at the Fitness Center, would be tapped for the skylight project.
Mottola said it’s hard to tell how much work will be needed until the existing skylights are disassembled, but she noted that the work shouldn’t cause any significant disruptions to activities inside the gym.
Angst over Gateway
proposal persists Six days after a contentious town hall meeting to explain a new proposal to eventually consolidate RWC and RWC Property Management staffers at Gateway, opponents of that concept came to the Planning Committee meeting, mostly protesting a preliminary proposition to relocate the Library.
The proposal would involve significant Dollar House renovations, in preparation for moving some meeting-room functions (including the current Redwood Room) from either the Gateway Clubhouse or from the Multipurpose Rooms. The MPRs, then, would under the current proposal become home to the Computer Center and the Rossmoor Library.
“The plan for the Library is a situation where the tail is wagging the dog,” David Kann told the committee.
Eight residents spoke against elements of this proposal, especially moving the Library out of Gateway Clubhouse. A few speakers said consideration of parking with any of these moves has been insufficient; others criticized what they said was the lack of public participation in that initial proposal. One speaker, Judith Schumacher-Jennings, said she didn’t see whether various rooms’ kitchens work into any plans. “Saving kitchens for the clubs is important,” she said.
Nancy Castille told the Planning Committee she believes critics’ behavior, including frequent interruptions, at the March 6 town hall was rude, and encouraged those critics to “cite grievances in a kind and productive manner” in the future.