Rossmoor News, February 18, 2026

Planning Committee signals interest in plan to evaluate Gateway as new home for RPM Dollar House also would see major renovations

Planning Committee signals interest in plan to evaluate Gateway as new home for RPM Dollar House also would see major renovations

By Sam RichardsStaff writer

In print on pages 1A and 13A

Two people walk toward the entrance of the Gateway clubhouse, a single-story building with a cupola and wooden beams.
The Board will consider a proposal to evaluate Gateway as the new hub for an administration building that would include relocating RWC Property Management from Rockview Drive.News photo by Dan Rosenstrauch

The future of Rossmoor could look quite different, especially at Gateway and Dollar clubhouses, as RWC tries to move its property management operations out of the overcrowded Rockview Drive offices.

The RWC Planning Committee recommended to the RWC Board last week that an architecture firm be paid up to $157,000 for a study of proposed renovations to Gateway’s Building F – which houses the Multipurpose Rooms – and to Dollar House to consolidate most RWC and RPM management functions at Gateway.

The recommendation, which ultimately must be approved by the full RWC Board, is to hire ELS Architecture and Urban Design, based in Berkeley, to help with the “design development phase” for both facilities. ELS was involved with the creation of RWC’s Facilities Master Plan, adopted in 2022, and more recently has been serving as project architect for the new pickleball building.

Relocating a consolidated home for RWC and RPM operations by 2032 is a top recommended project in the Facilities Master Plan but has proven challenging. After several other options were investigated over the past few years, the plan now is to move those functions to Gateway. That would require finding new homes for the Rossmoor Library, the Computer Center and the Redwood Room. Now being considered is converting the existing multipurpose rooms in Gateway’s Building F into new homes for the library and Computer Center.

But first, the Dollar House renovations would have to be completed, which would allow Dollar to assume some of the meeting room demand now met in MPRs 1, 2 and 3. Those renovations would entail opening up more rooms, including upstairs, for meetings, and installing an elevator to that second floor.

Then, the Gateway multipurpose rooms could be remodeled into a new library and computer center. Finally, under this preliminary plan, Gateway buildings B and C could be converted into new administrative offices, a City Council-style chambers/meeting room, a central reception desk and Food and Beverage service offices.

RWC General Manager Jeff Matheson said the nuts and bolts of these various proposed changes will be discussed at a Friday, March 6 town hall meeting at the Event Center. He said there also will be future public workshops on the topic.

The renovations, once they’re approved, would be financed by proceeds from the sale of the RWC-owned building at 1220 Rossmoor Parkway. This is the former John Muir medical building, which has been vacant since 2019. It almost sold twice previously, and Matheson said that property is again in escrow with a sales price at $17.2 million.

Both Matheson and Planning Committee Chair Dwight Walker praised the “one-stop shopping” aspect of consolidating RWC and RPM management in one building; Matheson said Laguna Woods Village, a 55-and-older community near Los Angeles, has similarly consolidated operations.

Committee member Adrian Byram liked that the new council chambers-style meeting room would be available to all Mutual boards to use.

The project’s effects on parking at Gateway and Dollar would be part of the initial study, Matheson said.

Plans call for Phase I of the ELS study, if approved, to be the design and public input process for the proposed Dollar House and Gateway (MPR) changes. Phase II would be creation of construction drawing and project permitting; Phase III would be construction at Dollar House and Gateway Building F, and Phase IV would be completion of the design and construction drawings for Gateway Buildings B and C.

This is a complicated project, Matheson said, with many moving parts, and would unfold slowly, if approved by the Board. Sequencing, he said, is critical.

Residents carrying shopping bags board a white Rossmoor Dial-a-Bus at the Rossmoor Shopping Center.
Residents board a Rossmoor Dial-a-Bus after shopping at the Rossmoor Shopping Center.News photo by Dan Rosenstrauch

“There are many, many steps that need to be planned out,” he said.

‘Short-range’ transportation plan In the ongoing effort to determine whether it’s possible for RWC to operate a bus service with enough service at a fair price to significantly increase ridership, the Planning Committee on Thursday voted unanimously to recommend the RWC Board seek a consulting firm to do a comprehensive study of Rossmoor’s transit operations, with ridership not having significantly rebounded

from declines stemming from the 2020 COVID shutdowns.

Current challenges to increasing service, according to a RWC staff report, include restoring rider interest and confidence; finding dispatch software that matches the desired future level of service; and recruiting and retaining bus drivers, which has been a challenge ever since the 2020 pandemic shutdowns.

Matheson said the hope is a consultant’s effort can show how RWC can attract more riders who have other transportation options, and not just “transit-dependent” residents.

Rossmoor leaders have been torn between responding to residents who say Rossmoor’s abbreviated transit offerings don’t offer enough service to make buses (or less expensive shuttle vans) worth the cost and answering to transit advocates who insist that for residents who rely on the service because of need, this isn’t a matter of choice.

The specific goals of the study, the staff report says, are to identify the market for riders using Rossmoor’s bus service; to propose service adjustments to better align with post-pandemic realities; to evaluate potential service adjustments with an eye toward attracting new riders; to evaluate options for dispatch software; and to evaluate vehicles that would be the best match for what is ultimately deemed the right service for Rossmoor.

Before the pandemic, Rossmoor buses ran on a schedule, seven days a week on several fixed routes. Ridership hit a high of 116,000 passenger trips in 2019. RWC now offers only Dial-A-Bus and paratransit service, five days a week. In 2025, RWC’s Transportation Department operated 36,000 passenger trips for residents.

As part of the RFP, the chosen consultant would be asked to evaluate ridership patterns and the ridership volume to various locations; conduct surveys of onboard ridership, host workshops, and administer online and physical community surveys to evaluate actual and desired needs of the community in relation to the transportation service.

The plan is for RFPs to be given to pre-selected potential consulting firms by April 1, with responses due by May 30. Those responses would be evaluated starting June 1, with final recommendation of a consultant to be considered by the RWC Board at its July meeting. The actual work would begin in early September.

Rossmoor sent out similar requests for proposals a few years ago, but had no takers, and no study was done. Matheson said he expects a better response this time, given the maximum approved financial outlay recommended now is $80,000; two years ago, the maximum outlay was $50,000.

Byram said RWC should be willing to have its transportation operation scrutinized from top to bottom, everything “looked at afresh.”

“It shouldn’t just be about how to fix what we’ve already got,” said Byram. If such scrutiny suggests something drastic – having an outside operator take control, for instance – Rossmoor should seriously consider drastic action, he said.