New EBMUD fresh water facilities will benefit Rossmoor
Grizzly Reservoir being replaced
By Tony HicksStaff writer
In print on page 28A

The East Bay Municipal Utility District (EBMUD) is working on two projects in the area as part of its broader East of Hills Facilities Demolitions and Improvements Project.
Grizzly Reservoir, built in 1965 and technically located in Lafayette at the end of Lucas Drive adjacent to Rossmoor Electrical Substation, is being replaced. Workers are replacing the current 4.8-million-gallon steel reservoir with two 1.3-million-gallon reservoirs to increase operational efficiency.
“We are reducing storage because our system analysis shows that the area does not need as much capacity as originally built,” said Christopher Tritto, an EBMUD spokesperson. “When water sits too long in a large reservoir, it can become stagnant and affect water quality.”
Tritto said replacing one large tank with two smaller reservoirs provides operational flexibility, keeps water fresher and allows the utility to take one tank offline for maintenance and operational adjustments while keeping the other in service.
“These changes will improve water service reliability,” Tritto said. “The upgrades were planned in coordination with local fire districts and will not impact firefighting capabilities.”
Workers are also demolishing EBMUD’s Castle Hill Reservoir and Regulator, which was built in 1980 and is located near residential properties on Grey Eagle Drive.

A new regulator will be built 250 feet from the old reservoir being demolished. Tritto said that move will reduce excess storage, improve water quality, and help control and stabilize water pressure for the surrounding service area.
“It regulates the flow of water traveling downhill from upstream storage facilities, such as the new Grizzly Reservoir, into the lower-pressure zones that serve customers,” Tritto said. “It will tie into existing water mains and upstream facilities and does not require its own replacement reservoir.”
Work is underway at both sites. Tritto said Rossmoor residents can expect major construction activity in both areas over the next six months.
The new facilities will include improved fall protection, safer access points for maintenance, and upgraded layouts to reduce confined-space hazards, and enhance overall worker safety.
Rossmoor receives EBMUD water from multiple interconnected facilities. The facilities on which work is being done support the system serving Rossmoor but are not its only supply sources.
The Rossmoor-related enhancements are part of the larger EBMUD project involving upgrades to several key water-distribution facilities east of the Oakland Hills. The larger project began in late 2024 with a 2.5-year target timeframe.