Pickleball project set to begin – up first, relocating irrigation lines
By Sam RichardsStaff writer

Staging for the first construction work connected with the new pickleball facility is set to begin the week of Oct. 13, and that will bring some temporary changes both to the 18th hole of the adjacent Dollar Ranch Golf Course, and to the parking lot that serves both the Event Center and Dollar Clubhouse.
During the week of Oct. 13, the 25 or so parking spaces immediately south of the Event Center and directly facing the 18th hole sand traps and putting green will be closed off with portable fencing, and a construction trailer/ office will be placed there, said Ann Mottola, Rossmoor’s director of community services. Construction supplies and work-vehicle storage will also take up what currently are parking spaces, she added.
Also, surveying of the site, and of the irrigation line, will begin the week of Oct. 13, Mottola said. The physical relocation of the irrigation line, farther west, out closer to the 18th hole’s southernmost bunker, will begin the following week, said Dave Gearing, Rossmoor’s construction manager, and should be done by the end of November. That means normal play on the 18th hole ‒ which will be temporarily reconfigured for the duration of the irrigation line work ‒ is expected to resume by that same date.
Mark Heptig, Rossmoor’s director of golf, said the main change to hole 18 to accommodate irrigation line relocation will be moving the green about 120 yards to the south. “We’ll be using the temporary green for about four to six weeks,” he said.
Disruption to golfers should be minimal, said Mottola, who noted that the start of work was delayed until a series of three golf tournaments is finished, by Oct. 20. Irrigation to the 18th hole and fairway likely will be out only two or three days, Gearing said.
Mottola said a formal groundbreaking for the pickleball facility is planned, probably sometime in November, though a date had not been set by press time.
Gearing said the pickleball facility is a “Butler building,” a prefabricated structure that will be assembled mostly on site; the plan is for much of that work to be done in February and March 2026. If all goes well, building construction should be finished by the end of June, he and Mottola said. In addition, its roof will host solar panels, their generating capacity adding to Rossmoor’s existing solar power footprint.

Construction vehicle traffic ‒ cement mixer trucks, carpenters’ trucks, other vehicles ‒ in and out of the Event Center parking lot, Gearing said, figures to be “on and off” between November and June, depending on what work is happening at the moment.
“We’re going to stay away from the (golf) tournaments,” and the significant added traffic they can bring, in an effort to minimize traffic problems, Gearing said. But he and Mottola acknowledge that there will be some disruptions in the Event Center parking lot through June, at least.
“We will make every effort to minimalize traffic in the lot, but that is where the deliveries will be made,” Mottola said.
On Aug. 28, the RWC Board’s voted to approve spending up to $4.49 million to move ahead with building the pickleball facility. That vote came after years of deliberation on where to build it, and robust community debate on how to make the noise from players (and their balls and paddles) as tolerable as possible and, more recently, whether spending $4.49 million on the structure was just too much.
In the end, Board members said, a good pickleball facility will attract new residents to Rossmoor, and will be an appreciated amenity for the 600 to 700 current members of the Rossmoor Pickleball Club, and other residents.
Mottola and Gearing assume that many Rossmoor residents will be following the pickleball facility’s construction progress, and that many also will have questions. To cater to all of them, Rossmoor is working to set up a project web page, updated regularly with construction progress information. The goal is to have that site up and running by the time work on the actual courts building is under way.