The following actions were taken by the GRF Board at the regular meeting on Oct. 31.
1. Approved an additional capital budget expenditure of $37,340 to increase the Golf Course Pump Replacement project budget to $112,340; and authorized the general manager to execute an agreement with Cornerstone Environmental Contractors, Inc. to perform the replacement work in an amount not to exceed $87,269, to be paid from the Trust Fund.
2. Authorized the general manager to enter into an agreement with the law firm of Beaumont Tashjian to provide general counsel services for the Golden Rain Foundation.
3. Approved the golf tournament schedule for 2025. 4. Appointed Ted Bentley to the Policy Committee, effective immediately, for a temporary term until Dec. 31, 2024.
5. Ratified Board action taken in executive session to authorize a contract amendment for the Pickleball project, with additional costs not to exceed $90,300.