Rossmoor News, September 25, 2024

Tice pools’ roof panel replacement set for October

Work will close the pool area starting on Oct. 21

By Mike WoodStaff writer

In print on pages 1A and 8A

A large glass and steel roof with retractable panels over the Tice pools, partly open to a blue sky.
The roof panels at the Tice pools will be replaced starting Oct. 21.News photo by Sam Richards

The wait to replace the aging, malfunctioning roof panel system at the Tice Pools soon will be over.

The target date to start the work is Monday, Oct. 21. The roof panels and the gears and motors that operate them will be replaced, said John Raith, Trust Maintenance supervisor.

The work will be done by OpenAire, a Canadian retractable roof company that built the original Tice Pool roof in 2007.

Powered by motors, panels on the roof are supposed to open and close. Since early 2023, one of the panels has been stuck open.

Ann Mottola, Rossmoor’s director of resident services, announced the impending work at the Sept. 12 Aquatics and Fitness Advisory Committee meeting. With that panel stuck open, it has created an odd spectacle when precipitation hits Rossmoor.

“It won’t rain inside Tice anymore,” Mottola said after the meeting. “We’re excited.”

The replacement work will result in the pools being closed starting Oct. 21. Classes, the most popular being water aerobics, will be temporarily relocated to either Hillside or Dollar outdoor pools, Mottola said. Detailed communication regarding those moves probably will begin this week, she said.

This also means that Dollar and Hillside pools, which typically close for the winter on Dec. 1, will remain open past that date while the Tice pool work is completed.

“We’re going to keep those outdoor pools open until we can open the indoor pool,” said Mottola, noting that will enable master swimmers and those in classes like the popular water aerobics to continue their workouts.

The extensive project is anticipated to continue through the end of December, Mottola said.

Delays have resulted from supply chain issues and permitting requirements through the city of Walnut Creek. Initial plans to perform the work in August 2023 had to be shelved.

Ideally, another capital budget project, the resurfacing of Tice Pool, would have dovetailed with the roof project. However, that vendor did not obtain permits in time and the contract was terminated, Mottola said.

New bids will be sought for that project, she said, and work will be done when the outdoor pools are again open, perhaps next spring.

Meanwhile, the locker rooms, shower area and pool and deck areas have undergone extensive maintenance work since summer, which Mottola explained in detail to the committee.

Another Fitness Center capital project, replacement of the original skylights over the center’s main exercise area, is being pushed to 2025 because that project would involve addressing environmental standards, she added.