Solar project begins Sept. 30 at Gateway
By Ann PetersonEditor-in-Chief
In print on page 4A
The Farmers’ Market will end for the season on Friday, Sept. 27, and half of Gateway’s parking lot will close starting Monday, Sept. 30, to begin installation on Phase II of the solar canopies.
Construction begins Monday, Oct. 7, on the north side of the Gateway parking lot, abutting Golden Rain Road. Installation in this first of two phases will close two rows of the double stalls on that side, with completion expected by Friday, Nov. 8.
The rest of Gateway’s parking lot will remain open during construction.
Because of the work, the Farmers’ Market – which usually ends in late October – will close for the season on Friday, Sept. 27.
Then construction moves to the next two sets of double stalls from Monday, Nov. 18 to Friday, Jan. 10; the fences will go up on Monday, Nov. 11. The parking stalls that were previously under construction will reopen during this phase.
Construction work will occur between 8 a.m. and 5 p.m. on weekdays. Project manager Fred Ponce said residents can expect construction noise to be loudest during the first two weeks of each phase.
After final connections and inspections, the solar panels could begin generating power around Jan. 20.
The plan will not block parking lot entrances/exits, EV chargers, the bus stop or back parking lot by the multipurpose rooms. It might affect the coupon box and drive-up mailbox; watch for future notices if this happens.