Rossmoor News, July 17, 2024

Latest updates on capital projects

By News staff

In print on page 6A

The following update on capital projects was presented to the GRF Planning Committee on Thursday, July 11. Monetary figures are the funds approved in 2024.

Gateway Phase II Studio renovation: ($160,908) Construction is complete. Final projects include solar shades and AV installation.

Pickleball courts: ($2,583,728; $300,000 projected to be spent in 2024) Permitting process is progressing with the final backcheck being circulated through Walnut Creek Planning and Engineering.

Tice Pool roof structure: ($132,706) Permits are in hand. Scheduling with pool replastering vendor is taking place. Anticipated start mid-September.

Alternate transfer pump for golf: ($21,594) Still awaiting parts Jenark replacement (capital portion of ERP):

($616,203) Implementation is underway. Finance is working on updated financial projections for the project.

Golf bridge replacement: ($142,553) BKF is almost complete with creek survey. Preliminary engineering will start after that.

Network gear replacement: ($491,16) Implementation is underway.

Tice Pools and spa replastering: ($170,000) Vendor is obtaining permit. Scheduling with pool roof vendor is taking place. Anticipated start mid-September.

Buckeye Tennis Court resurfacing: ($75,000) Resurfacing is rescheduled to start the week of July 15. The work will take approximately two weeks.

Community Services Director Ann Mottola said staff also is actively looking for a vendor to complete much-needed repairs because of cracks in the pickleball courts.

Event Center Tech/AV rehab: ($199,360) Work is scheduled for the month of September.

Pavement program: ($960,000) Bid packages have been received and are being evaluated. Contract scheduled to go to Board at July meeting.

Roof replacement program: ($165,000) Bids are being obtained.

Median turf replacement: ($65,000) Funding approved at June 29 Board meeting.

Golf course pump replacement: ($75,000) Funding approved at June 29 Board meeting.

Golf course lake liner replacement (scoping study): ($50,000) Funding approved at June 29 Board meeting.

Gateway solar array: ($17,277) GRF is reviewing the PPA. A disruption plan is being developed with a phased installation plan so there will be only partial parking lot closures for the duration of project.