Some GRF capital projects to carry over to 2024
By News staff
In print on page 4A
The following update on capital projects was presented to the GRF Planning Committee on Dec. 14. Only items with changes are noted.
Jenark replacement project: The $916,203 capital portion of the project are costs associated with customizations, data conversion, system configuration and report programming. An agreement was signed in November with NetSuite. Project will be carried over to 2024.
Pickleball project: Funds were approved in 2022 to initiate the construction of a new pickleball complex and increased in the 2023 capital budget to add a building enclosure. The project is estimated to cost $2.9 million. Staff continues to work with Walnut Creek City Planning Department for project review. Project will be carried over to 2024. Project is expected to go out to bid in January. Construction is slated to start in March with a late summer or early fall completion.
Golf drought projects: The $130,000 project is complete for 2023. Addiitional areas will be requested in carry-over to 2024.
Golf bridge replacement: The bridges are scheduled to be replaced over a 10-year span, and this is the first scheduled replacement. The $150,000 project is being scoped by a project manager. The consultant will need to coordinate with Army Corp of Engineers, Regional Water Quality Control Board, California Department of Fish and Wildlife and the U.S. Fish and Wildlife Service. The project will need to be approved in the 2024 capital budget process in order to proceed.
Buckeye Tennis Court resurfacing: The tennis courts need resurfacing as cracks and rust spots are beginning to impact play. Rust spots very likely coming from aggregate in asphalt pavement containing high levels of mineral pyrites. Options for resurfacing are being investigated. Options for the project scope and phasing will be addressed as part of the 2024 capital budget process. Cart path replacement: The $15,000 section of the cart path that was slated for 2023 will be complete this year.
Medical Center $160,000 In April 2023, the GRF Board approved $160,000 to complete an evaluation of the Medical Center Property for potential reuse for MOD, Accounting, and other GRF offices. Dec. 1 Update: ELS is preparing a summary of the Space and Programming Study and Rockridge Geotechnical continues to evaluate ground movement over the course of this next year to evaluate whether the property can potentially be used for MOD, Accounting and other GRF offices.
Gateway phase II studio renovation: A $1.858 million contract was awarded to Oak Park Construction for renovation of the Lapidary, Woodshop and Art studios. Staff is auditing the project budget as there was machinery and equuipment expense charged to this project’s Capital Budget in error. Project completion and audit by the end of December 2023.
New roof structure for Tice Pools: Staff continues to work with Walnut Creek Building Plan Review for additional information required for the project to be permitted. Project will be carried over to 2024.