Renovation update: Lapidary close, Woodshop is behind
By Sam RichardsStaff writer

Al Kaufman said he gets one or two calls each day from people asking when the Woodshop will reopen. And most, he said, aren’t even from people who use the tools and machines there.
“We do a lot of knife sharpening, furniture repair … we call it the ‘community work,’” said Kaufman, one of 32 “supervisors” who watch over operations in the Woodshop. “We even fixed a didgeridoo,” a wooden woodwind instrument that originated with Aboriginal Australians.
“People bring projects to us all the time,” said Kaufman, noting that the Woodshop workers do not do finishing work.
The Woodshop at Gateway, along with the neighboring Lapidary Studio, both closed in December ahead of thorough renovations and updating as part of Phase Two of the Gateway studio renovations. And now, the $1.858 million project is approaching completion, with the Lapidary Studio a bit further along than the Woodshop.
“We’re really close now,” Carol Lehr, president of the Lapidary and Jewelry Club, said last week. “This place was just old; it hadn’t been touched in 30 to 40 years.”
The main work being done, Lehr said, involves improvements to lighting and storage lockers, new display windows (still awaiting glass at press time), new flooring and roll-up back door and resurfaced tables.
Lehr said last week that the fire and building inspections for the Lapidary Studio had taken place, and only a few “minimal” issues remain to be resolved. She said she hopes club members can start moving things back in this week.
The overall work was close enough to completion that, on April 29, the club opened the space up to the public for a special sale of club members’ art pieces.
“I think we got everything we wanted,” Lehr said. “Basically, I think everything’s going to be great.”
Work at the Woodshop is moving a bit more slowly, said Kaufman, who is hoping for a mid-July opening. The shop will have a new electrical system, a new dust-collection system, new floors, improved lighting and a new ceiling.
“I’ve been in construction my whole life – I knew it would take this long,” said Kaufman, who added that the wait will be worth it.
The Art Association Studios are also part of the Phase II renovation project but are receiving less extensive work than either the Woodshop or Lapidary areas.
Fred Ponce, a consultant with ArcPath hired by GRF to consult on this and other GRF capital projects, told the GRF Planning Committee on June 8 that he expects both the Lapidary Studio and the Woodshop to achieve major milestones by mid-July. That won’t be the end of things, though, he predicted.
“Both groups will have a lot of ‘move-in process’ before starting classes,” Ponce said.
Phase One of the studio renovations at Gateway included the Ceramic Arts and Sewing Arts spaces; it started in July 2021, with both groups moving back in March 2022.