EBMUD pipeline work set for Grey Eagle
By News staff
In print on page 9A
The East Bay Municipal Utility District (EBMUD) is planning to begin work next week on a project involving Rossmoor’s Grey Eagle Drive to upgrade the area’s water system.
According to EBMUD, the project will include installing approximately 1,700 feet of new 12-inch and 8-inch diameter pipes, connecting the end of Grey Eagle Drive to the southern end of Castle Crest Road.
The pipeline installation on Grey Eagle Drive is expected to begin Monday, June 26, and last through September.
Residents may notice EBMUD crews on Grey Eagle marking the street and an increase in EBMUD trucks during this period.