Capital projects: Paving eyed for summer start
By News staff
In print on page 4A
The following update on capital projects was presented to the GRF Planning Committee on May 11. Only items with changes are noted.
Paving: The $600,000 street paving project is tentatively scheduled for the summer. The bid package preparation is in progress.
Golf drought projects: The budget for this project was reduced from $350,000 to $130,000 for 2023. The funds will cover conversion of two non-functional turf areas and approximately five to seven tee boxes, with work slated to start in July.
Golf bridge replacement: A proposal was received from the civil engineer, who will provide the overall construction document services for the bridge and alterations. Next steps include approving two consultant proposals and coordinating a project kick off meeting.
Buckeye Tennis Courts refacing: Rust spots are likely coming from aggregate in asphalt pavement containing high levels of mineral pyrites. Options for resurfacing are being investigated.
Median island turf replacement: Staff is determining project scope and preparing the bid package.
Carpet replacement at News: The new carpet has been installed.
New roof structure for Tice Pools: The poly window panels are being worked on while waiting for the arrival of new motors for the sliding panels.
Alternate transfer pump and piping: The project will help capture runoff and drainage water before it reaches Tice Creek for use on the golf courses. The motor has been built and delivery is expected soon.