GRF NEWS

PLANNING: Update details capital projects

News photo by Dan Rosenstrauch A golf cart rides over the bridge at No. 6 on Creekside that was damaged by erosion from flood waters over the years and now needs major repairs.

Continued from page 1A is just for the building,” Ponce explained. “The paths, fencing, courts, landscaping are not figured out yet. That’s what we’re working on. If I find out that all (the current contractor) does is butler buildings, then we will find a different contractor to do the comprehensive cost estimate.”

General Manager Jeff Matheson added, “We might spend a little more for construction of the facility, but then we would have better savings for solar.”

Committee member Ted Bentley asked whether the pickleball facility could be built first, followed by solar, which sometimes takes longer to complete because of permitting.

“The benefit of this method is that we build the building (for pickleball) and then take advantage of the roof,” Ponce said.

Once a comprehensive estimate is approved by the Board, Ponce said, it likely would take two months to complete drawings and then three months for permitting, with bidding happening at the same time.

“I know it’s been a long project,” Matheson said. “We will get there.”

Matheson also updated the other capital projects, noting that starting in March, Ponce will begin delivering the report to the committee. Matheson said Ponce has met with staff and consultants to review the list of projects and their status.

The most expensive and complicated capital project involves the approximately $916,000 Jenark software re-

BRING THIS AD FOR $15.00 OFF ANY SERVICE $ $

(925) 942-3677

franksautoservice.com 1255 BOULEVARD WAY – ACROSS FROM 7ELEVEN

One-Stop Auto Care That You Can Always Count On. Frank’s Auto Service

Dave Frank

No it’s not house Cats. It’s actually Catalytic converters from your vehicle. Every car has one but right now the Toyota Prius is the one that every thief wants. We have seen it happen overnight and even had a Rossmoor customer who was at a doctor’s appointment for 45 min in the middle of the day and when they came out, their catalytic converter was gone. It’s taking these thieves minutes to cut out the catalytic converter and disappear. We are now offering a solution to deter this theft. We will install a protection plate on your vehicle to keep your catalytic converter safe. If you have a Toyota Prius give us a call so we can keep your Cat safe.

For Walnut Creek & Rossmoor residents over 65,

we offer vehicle pickup and drop off.

If you have any questions or concerns or would like to make an appointment, please give us a call at 925-942-3677.

You might have

heard about an increase in

CAT thefts in the Bay Area

placement, which began this month with the Pemeco Consulting team holding kickoff meetings with key staff. Jenark is the system used for work orders, membership records, accounting and more.

Matheson said it will take about three months for the consultant to assess staff needs and identify systems that fit those needs.

“We had a roundtable where staff shared initial insights and issues,” Matheson said. “With Jenark, it’s just amazing the workarounds staff has had to do and the frustrations each department has faced. I’m very much looking forward to the improvements ahead of us.”

Also underway are the $896,050 renovations on the lapidary and art studios and woodshop. Demolition is complete, and installation of new flooring was scheduled for last week, Matheson said. Unlike the first phase, which renovated the ceramic and sewing studios, Matheson said, they have encountered fewer supply-chain issues.

But Bentley noted that residents have been coming on site to request changes of the contractor. Matheson assured the committee that changes can come from only the designated manager for each studio.

“The contractor does not take direction from individual residents,” Matheson said. “It doesn’t work that way.”

Matheson also updated the other capital projects:

• A paving project ($600,000) postponed from 2022, which will cover sections of Skycrest Drive and

Upper Golden Rain Road, is tentatively scheduled for late spring or fall.

• The golf drought projects ($350,000), which include reducing turf around three to five golf tee boxes and bordering the golf courses in several locations, have taken a back seat to course repairs needed because of the winter storms.

• Access control phase III ($200,000) will include adding a pedestrian gate at the main entry and a security gate at the bottom of Rockview Drive. Ponce and staff will evaluate the proposed designs for the gates and present them to the Planning Committee in late spring.

• Completing Dollar Patio ADA upgrades ($175,000) is under review by Ponce.

• Golf bridge replacement ($150,000) has undergone a very preliminary review of the bridges to determine scope and professional resources that may be involved.

• Buckeye Tennis Courts resurfacing ($125,000) will be evaluated in the coming weeks to prepare bid documents.

• Preliminary designs are ready for a median island turf replacement ($80,000) between Golden Rain Road and Terra California Drive on Rossmoor Parkway.

• Replacing carpet at the Rossmoor News ($50,000) will be scheduled for later in 2023.

• Hand dryers and electrical at the Event Center ($20,000)

are out to bid.

• Replacement of a portion of the roof at Peacock Hall ($20,000) has yet to be scheduled.

• Cart replacement ($15,000) on the golf courses will take place as needed.

Among the 2022 carryover projects:

• A new roof for Tice pools ($187,855) is expected to come in summer or early fall. The roof panels are in, and the motor is expected in May.

• Water reclamation facility study ($158,660) is currently on hold pending further consideration of the project.

• Access control system phases I and II ($20,018 and $74,547) have included development and data clean-up for the central database and improvements to the front gate, Mutual Operations Depart-

ment (MOD) and portions of Gateway and the Rossmoor News.

• Work on an alternate transfer pump and piping to capture runoff and drainage water for the golf course ($58,193) will take place after the courses have dried out.

• Revision of trust agreement ($30,000) is on hold.

Gateway large conference room upgrade ($22,318) is complete, with final invoicing pending.

• Consulting contract for solar array ($2,619) is for independent consulting to evaluate agreements and proposed plans for the Phase II solar project.

The Planning Committee will meet next on Friday, March 10, at 10:30 a.m. in the Board Room at Gateway and on Zoom.