Rossmoor News, November 23, 2022

GRF NEWS

Closer look at recommended GRF 2023 capital budget items

By Ann PetersonManaging editor

In print on page 7A

The following are the capital projects and machinery and equipment (M&E) items the GRF Planning Committee has recommended that the full GRF Board approve as part of the 2023 capital budget. The Board will review the list of recommendations and vote to approve the budget at its endof-year meeting on Thursday, Dec. 1.

The meeting will be held at 9 a.m. in Peacock Hall and on Zoom.

• Jenark replacement project – $916,203 for the capital portion of the project, which includes customizations, data conversion, system configuration and report programing. The operating portion of the project has already been approved. The capital costs are estimates based on detailed discussions with four consulting firms. However, the estimated costs associated with customizations are very fluid and will not be determined until the new system is selected.

• Roof for Peacock Hall – $20,000 to replace the roof on the existing theater building at Gateway.

• Replace carpet at Rossmoor News – $50,000 to move furniture and replace worn carpet in the Rossmoor News and Television office.

• Buckeye Tennis Courts resurfacing – $125,000 for resurfacing because of cracks and rust spots that are beginning to impact play.

• Paving – $600,000 for paving approved for 2022 that was postponed and will be completed in 2023. (There will be savings in the 2022 capital budget of $570,000.)

• Golf bridge replacement – $150,000 for the first scheduled replacement of golf bridges that are scheduled to be replaced over a 10-year span.

• Cart path replacement – $15,000 for sections of the cart path that are replaced on an annual basis.

• Extra funding for pickleball – $600,000 is the estimate of additional funding needed for the construction of pickleball courts near the Event Center. Final funding requirements will not be known until plans are complete.

• Median island turf replacement – $80,000 to replace the median island turf between Golden Rain Road and Terra California Drive.

• Golf drought projects – $350,000 (of $550,000 requested) to complete drought master plan, reduce turf around some golf tee boxes and replace turf bordering the golf course in several locations.

• Access control phase III – $200,000 to add pedestrian gates at the main entry as well as a security gate at the bottom of Rockview Drive.

• Hand dryers and electrical at Event Center – $20,000 to replace paper towels with hand dryers as restrooms at the Event Center back up many times per year due to paper towels flushed in the toilets.

• Dollar patio improvement project – $175,000 for a project identified in the Facilities Master Plan to complete ADA upgrades to the back patio.

The following M&E items also were recommended:

• Golf equipment – $175,000 for a Landpride OS1572 72-inch width overseeder ($25,000) and new fairway mower ($150,000).

• Trust vehicle – $50,000 to replace a Custodial truck.

• Dust control improvements for woodshop – $75,000 for a sprinkler system, configuration of several explosion-containment and relief valves and motor upgrades as part of the dust-collection system. Contra Costa Fire Protection District required GRF to complete a Dust Hazard Assessment at the woodshop, and the subsequent report showed several areas that are out of compliance with current fire safety code, which must be met for the woodshop renovation to proceed.

• MOD vehicle – $70,000 to replace MOD Landscape truck.

• Baracuda BU – $70,000 for a device that takes snapshots of the virtual servers, enabling GRF to restore an entire server or just a file that someone accidentally deletes. The current Barracuda 690’s warranty and license are set to expire Jan. 10, and it is undersized for GRF’s current environment, which has grown from 10 terabytes (TB) of space to 21 TB, with additional growth expected in the next five years.

• Host servers (3) – $60,000 to replace the current five-yearold host servers, which are out of warranty and beyond their dependable life expectancy. Some repair parts are no longer manufactured and would have to be acquired from resale markets. Each host server handles computing for several production virtual machines (servers), and a hardware failure would impact employees’ daily work.

• 5 PC laptops with associated accessories – $10,000 to replace Mac desktop computers used to produce the Rossmoor News with PC laptops that would allow the News to work remotely, if necessary. The Macs had significant technical issues in 2022, requiring outsourcing for IT support. They also have compatibility issues with other GRF computers.

• Pool heater – $15,000 to replace one of the two heaters needed at Dollar pool. These heaters last approximately two years because of the higher pool water temperature required. Every year, funds are requested to replace one of the heaters.

The Planning Committee recommended removing the following items from the 2023 capital and M&E budget:

• Golf drought projects – removed $200,000 from the requested $550,000.

• Public safety improvements – $60,000 for additional speed readers and improvements on Rossmoor Parkway.

• Replace chairs at Creekside – $55,000 to replace the 12-year-old and badly stained chairs at the clubhouse.

• Bocce safety and lighting improvements – $20,000 for the Bocce Club’s originally requested new handrails and lighting to complete a renovation project that included installing artificial turf this year.

• Two proposed utility vehicles – $90,000 as part of the M&E budget.