Capital projects: Solar likely starts in spring
By Jeff MathesonDirector of Resident Services
In print on page 7A
The following update on capital projects was presented to the GRF Planning Committee on Nov. 10.
Water reclamation: GRF hosted a well-attended regional Town Hall with EBMUD and Central San on Oct. 26. Several elected officials also were in attendance.
Solar phase II: Preliminary plans for the Gateway parking lot were revised based on feedback from the city and resubmitted. Plans for the Event Center location are pending the design of the pickleball courts with the solar canopy. Renderings for the Gateway parking lot site have been prepared and shared with the boards of First Mutual and Fourth Mutual. The project is estimated to be complete in early spring 2023.
Pickleball: The design team is working on the site development plans for submittal to GRF for review. The plans are scheduled to go to the city for initial review by late November. The tentative schedule for plan development is as follows: 50% schematic design submittal for client review, started Oct. 26 and due Nov. 17; 100% design review submittal to city, starts Nov. 17 and due Nov. 29; city review should be complete by Dec. 23; first planning resubmittal on Dec. 23 and sent to city for review on Jan. 13.
If a second submittal is necessary, the planning permit then should be received by March 3.
Gateway Studios: The GRF Board awarded a construction agreement to Oak Park Construction for completion of the renovation project. The city permits are complete, but per the Fire District, a dust hazard assessment is required for the Woodshop, which has resulted in additional conditions that must be met related to the sawdust collection system. The plans are being revised to meet the new code requirements. The clubs will begin packing the studios over the next four weeks with construction scheduled to begin Dec. 1.
Access control: Training on the new gate systems is still in progress. Securitas will work with the new access systems before rolling out to the community. Information has been published in the Rossmoor News and an informational presentation was conducted for clubs at the last Activities Council. Additional information is being mailed to club representatives.
Alternate transfer pump and piping: The second phase involves installing the conduit and electrical service, followed by the development of the intake structure and installation of pump equipment. This work will be scheduled for late 2022 or early 2023.
Roof structure for Tice Pool: The roof panels are scheduled to arrive this month. The motors for the retractable roof are still several months out. Staff will work with the Aquatic Advisory Committee on plans to open the outdoor pools should Tice be closed during any of the months where only Tice is open.
Median island conversion phase II: Work is underway on the section between Saklan Indian and Stanley Dollar drives on Rossmoor Parkway. The removal of the turf is complete. New drought tolerant landscaping is being installed to match the other median conversions.
Pedestrian safety projects: Of the two approved pedestrian safety projects, work at the intersection of Golden Rain Road and Oakmont Way has been complete. The addition of speed warning signs and crosswalk improvements will begin in the near future as plans are finalized and agreements signed for areas along Tice Creek Drive.