Rossmoor News, October 19, 2022

GRF NEWS

Capital projects: Water reclamation paused, access control continues Fitness Center roof work still delayed by supplies

By Jeff MathesonDirector of Resident Services

In print on page 7A

The following update on capital projects was presented to the GRF Planning Committee on Oct. 13.

Water reclamation: GRF Board President Dwight Walker and Board members Carol Meehan and Maxine Topper met with local agency representatives to plan a town hall event about recycled water for the central county. The town hall is scheduled for Wednesday, Oct. 26 at 11:30 a.m. at the Veterans Hall in Lafayette. During the Sept. 29 Board meeting, the Board voted to remove site No. 6, Cactus Garden location, from the areas of consideration for a future Satellite Water Recycling Facility. The Board also voted to pause further work by the consultant team on the development of a SWRF and referred the item back to Planning for discussion of potential regional alternatives at the November meeting.

Solar phase II: Plans for the Gateway parking lot have been submitted to the city for permit. Preliminary feedback has been received and revised plans submitted. Plans for the Event Center location are pending the design of the pickleball courts with the solar canopy.

Pickleball: See the Planning Committee article in today’s News for details on this project.

Gateway Studios: The Contra Costa Fire District is requiring a dust control report for the woodshop, which has been scheduled. Responses have been made on the second round of comments from the city. See the Planning Committee article in today’s News for more details on this project.

Access control: Training on the new gate systems has begun. Securitas will work with the new Access systems before rolling out information to the community. Once implemented residents will be able to update their information and guest lists online. The new systems will add a layer of security for tracking vehicle entry and exit from the community. Staff is preparing an information campaign for clubs and residents that hold events with non-resident guests. Information will be presented at the Activities Council and in the Rossmoor News.

Pond liner: Patch work continues to hold with additional patch work planned for the end of the season. Full replacement of the liner needs to be scheduled in the near future.

Alternate transfer pump and piping: Installation of 680 feet of 6-inch diameter piping has been completed. The next phase is to install the conduit and electrical service, followed by the development of the intake structure and installation of pump equipment, which will be scheduled in late 2022 or early 2023.

Roof structure for Tice Pool: The roof panels are scheduled to arrive in November. The motors for the retractable roof are still several months out. Scheduling will be determined over the next few months.

Median island phase II: The next phase of median island conversion will be the section from Saklan Indian to Stanley Dollar. At its September meeting, the Board authorized a contract to proceed.

Pedestrian safety improvements: The Board approved two projects. Work at the intersection of Golden Rain Road and Oakmont is complete. The addition of speed warning signs and crosswalk improvements will begin in the near future on Tice Creek Drive.