Capital projects update: Solar permits submitted for Gateway

Plans for Phase II of Gateway Studios’ renovations also submitted for permits

By Jeff MathesonDirector of Resident Services

In print on page 8A

The following is the Capital Project Update for September, which was presented to the GRF Planning Committee on Sept. 8.

Water reclamation Staff and the consultant team presented site information and a recommendation for site No. 5 (golf maintenance yard) and site No. 6 (open space known as the Cactus Gardens) in order for the Planning Committee to make a recommendation on the preferred site for the Satellite Water Recycling Facility. (See the Planning Committee article in this week’s News.)

Solar Phase II Plans for the Gateway parking lot have been submitted to the city for permit. Preliminary feedback has been received and revised plans submitted. Plans for the Event Center location are pending the design of the pickleball courts with the solar canopy.

Pickleball The GRF Board authorized an agreement with Jett Landscape to complete the design and construction documents for the Event Center site. The Board also approved an agreement with Acoustics Group to complete a sound study for the location. (See the Planning Committee article in this week’s News.)

Gateway Studios Phase II plan for lapidary, woodshop and art studios have been submitted for permitting. Comments have been received and addressed. Plans were resubmitted by Sept. 2. Staff has been working with Oak Park Construction, who is the contractor that completed Phase I, in order to do some value engineering. Working with the contractor before award of a bid will help identify areas where savings can be achieved in order to keep the project within budget. Oak Park is familiar with the designs and materials specified from completing Phase I.

Access control Training on the new gate systems has begun. Securitas will work with the new access systems before rolling out information to the community. Once implemented residents will be able to update their information and guest lists online. The new systems will add a layer of security for tracking vehicle entry and exit from the community.

Pond liner at golf Patch work completed by Golf Maintenance staff is holding. The patch work will be monitored throughout the summer. Some additional patch work is planned for the end of the season. Full replacement of the liner will need to be scheduled for the near future.

Alternate transfer

pump and piping Installation of 680 feet of 6-inch diameter piping has been complete. This is the first phase of the work. The next phase is to install the conduit and electrical service followed by the development of the intake structure and installation of pump equipment.

Roof structure for Tice pool

The roof panels are scheduled to arrive in November. The motors for the retractable roof are still several months out. Scheduling will be determined over the next few months.

Median island con-

version phase II The next phase of the median island conversion is scheduled for the fall. The next section is Saklan Indian to Stanley Dollar.

Pedestrian safety projects

Planning Committee and the GRF Board approved two pedestrian safety projects. The intersection of Golden Rain Road and Oakmont has begun with the installation of some concrete footings for the signs. Installation of the signs and flashing warnings began in early September (See the article in this week’s News). Stripping of the intersection will follow.

The addition of speed warning signs and crosswalk improvements will begin in the near future as plans are finalized and agreements signed for areas along Tice Creek Drive.