Rossmoor News, August 17, 2022

GRF NEWS

GRF Capital Projects Update: Permitting underway for solar, art studios

By Jeff MathesonDirector of Resident Services

In print on page 9A

The following is the Capital Project Update for August, which was presented to the GRF Planning Committee on Aug. 11.

Facilities Master Plan The Final Facilities Master Plan was adopted by the GRF Board on July 28. The plan has been posted to Rossmoor.com (https://tinyurl.com/ytsa2anr). The plan will now be a component of the development of the annual capital budget and a tool for long-term planning.

Water reclamation Staff provided the Planning Committee and the Board with an update on the project and the current cost estimate. The Board authorized staff and the consultant team to continue with the current scope of work in the Bowman agreement. This will provide significant progress on the CEQA process as well as the development of the project description to the point where proposals can be sought for a Water Purchase Agreement or a Design Build proposal. The Board also authorized the president to send a letter to elected officials, potential partner cities as well as Central Sanitation District and EBMUD, urging a regional solution to recycled water demands.

Solar phase II Plans for the Gateway Parking lot have been submitted to the city for permit. Preliminary feedback has been received and revised plans submitted. Plans for the Event Center location are pending the design of the pickleball courts with the solar canopy.

Pickleball The GRF Board authorized an agreement with Jett Landscape to complete the design and construction documents for the Event Center site. The Board also approved an agreement with Acoustics Group to complete a sound study for the location. The sound study was conducted July 12 and 13. The consultant placed five monitors in the surrounding area to measure ambient noise for a period of 24 hours. The consultant then simulated the added sound of pickleball on six courts. Mitigation measures are being developed and will be incorporated into the design. An updated design with sound study results will be presented to the Planning Committee and the Board for approval before proceeding with the final plans and permitting.

Gateway Studios Phase II plan for lapidary, woodshop and art studios have been submitted for permitting. The initial review can take 3 to 4 weeks for comments. As of this report, comments have only been received from Central Sanitation District.

Access control Work is near completion on installation of hardware at the Mutual Operations Department and at the front gate. An information and training program has begun for staff with the community to follow. The Board authorized an agreement with BPM for project management support to help with integration and data clean-up. The project manager has been meeting with staff and consultants over the past several months.

Pond liner at golf Patch work completed by Golf Maintenance staff is holding. The patch work will be monitored throughout the summer.

Alternate transfer

pump and piping Installation of 680 feet of 6-inch diameter piping has been complete. This is the first phase of the work. The next phase is to install the conduit and electrical service followed by the development of the intake structure and installation of pump equipment.

Roof structure for Tice Pool

The current lead time for the motors for the roof structure is over 40 weeks. A deposit has been paid and agreement signed. The work will be scheduled for late 2022 or early 2023.

Median island con-

version phase II The next phase of the median island conversion is scheduled for the fall. The next section is Saklan Indian to Stanley Dollar.

Pedestrian safety projects Planning Committee and the GRF Board approved two pedestrian safety projects. The intersection of Golden Rain Road and Oakmont has begun with the installation of some concrete footings for the signs. Installation of the signs and flashing warnings is pending delivery of supplies. Stripping of the intersection will follow. The addition of speed warning signs and crosswalk improvements will begin in the near future as plans are finalized and agreements signed.