Second phase of Gateway studio renovations is imminent
By Sam RichardsStaff writer

Al Kaufman doesn’t know yet exactly when it will happen, but he will appreciate the planned improvements to the Woodshop in the Gateway art studio complex. It will include an expanded tool room, updated electrical and dust collection systems, a relocated entry and room for more machines, thanks to a revised layout.
“We’ll be able to install some new equipment, including a panel saw, which will allow us to better handle large sheets of plywood,” said Kaufman, one of 32 “supervisors” who watch over operations in the Woodshop. “We don’t even have coffee in there – no room – and now we might even have room for a coffee maker.”
Continued renovation of Gateway’s art studios is among the projects approved by the GRF Board as part of the 2022 capital budget. This second phase of the Gateway studio renovations also will include improvements to the lapidary studio and the Rossmoor Art Association studio. The GRF Board has approved $950,000 for the work.
The first phase of the Gateway renovations, which covered improvements of the Ceramic Arts and Sewing Arts spaces, started in July 2021. Both groups moved back into their spaces in March.
“The studios had not been updated for a long time, and they’re in high demand,” said Jeff Matheson, Rossmoor’s director of resident services. “We’re maximizing useable space and providing some updated ‘finishes.’”
The main improvements to the lapidary studio, home to the Rossmoor Lapidary and Jewelry Club, will be new floors and lighting, new storage lockers and, perhaps most importantly, new display windows, allowing the public to see the lapidary work and jewelry from outside.
“It will be much more pleasant to work in there; it will be nice and fresh,” said Carol Lehr, a member of the Lapidary and Jewelry Club board and a longtime advocate for this project. The kilns also will be rearranged, she said, making it easier for the club’s 107 members to work on their pieces.
The display windows, Lehr said, will be a real key, allowing people to see the pieces created there (many of them for sale) when the studio is not open.

The architectural plans for the lapidary studio work are done, Lehr said. With COVID- 19’s arrival, earlier approval for some of the work, which had been granted, lapsed, and the process for some city permits has had to start over.
Kathleen Stumpfel, president of the Rossmoor Art Association board, said the Phase 2 work at the RAA space isn’t as extensive as in some other art rooms – “they’re just changing a few things,” she said. But those things include new window shades, upgraded and larger bathrooms, updated storage and renovated lockers. That work will create more organized storage room for RAA’s 350 members and also make the bathrooms Americans with Disabilities Act compliant.
This is helpful, Stumpfel said, for a club that has classes, demonstrations, open studio time and other activities several days a week.
“We got new lighting last fall, and the changes are appreciated,” she said.
Matheson said much of the planning for both phases of the work started in 2018, and that approvals were working their way through the usual processes when COVID hit in mid-2020. He said the plans have gone through some “minimal tweaking and updating” to reflect slight priority changes in the past couple of years. Permits from the City of Walnut Creek, the Contra Costa County Fire Protection District and the Central Contra Costa Sanitary District need to be approved, and Matheson said he doesn’t anticipate any unusual barriers there. And Lehr agrees.
“We’re hopeful that it won’t take that long – basically, they’re the same plans submitted before COVID three years ago,” she said.
Whatever that time frame, Kaufman said, it will be worth the wait.
“We’re really looking forward to the new arrangements and the improvements that go with them,” he said.