Rossmoor News, May 25, 2022

Planning Committee wants comparison of costs for three pickleball sites

By Ann PetersonManaging editor

In print on pages 1A and 12A

A golf course fairway with sand bunkers and a golf cart, with homes and tree-covered hills beyond.
The area being considered for a new pickleball facility is seen from the back of homes across the 18th hole of Dollar Ranch Golf Course.News photo by Dan Rosenstrauch

Asite behind the Event Center has officially entered the mix for consideration as the new location of a pickleball facility. But before labeling any location as a front-runner, the Planning Committee wants to see cost estimates for the three sites still in contention.

During last week’s meeting, the Planning Committee asked Director of Resident Services Jeff Matheson to draw up a comparison of cost estimates for a pickleball facility at Creekside, Buckeye and this new site.

Matheson cautioned that the estimates likely would be very high as they would contain every variable, including things like additional parking and restrooms.

“I’m a guy that likes to see all of our options, at least estimated out, in order to make an educated decision,” committee member Dwight Walker said. “Estimates of the three sites, even if they are crazy and wild in terms of being too high, would be very valuable in making a decision.”

Matheson said he was unsure how long the comparison would take or if it would be ready in time for the committee’s next meeting on June 23.

The new site proposal includes six courts in an open space between the Event Center parking lot and fairway for the 18th hole of the Dollar Ranch Golf Course.

Matheson ticked off a list of advantages that the new site offers for pickleball, including the existence of adequate parking, restrooms and social gathering areas near the proposed facility. The location also would have limited impact on other existing activities and facilities, as well as offering a built-in shade structure as already approved solar panels could be placed over the courts instead of the Event Center parking lot.

Those benefits are appealing as up until now the committee and GRF Board have faced relentless criticism from residents because of the other proposed sites. Initially, the GRF Board voted to renovate the current pickleball courts, but soil studies showed significant issues because of the nearby creek, which drove the projected renovation costs into the neighborhood of $1 million. In its search for a less expensive alternative, the committee and Board faced resistance for proposals to build on the Dollar picnic grounds, to replace two tennis courts at Buckeye or to utilize one of lawn bowling’s three greens.

That doesn’t mean the new proposed site behind the Event Center is without its critics or disadvantages, too.

The site would accommodate only six pickleball courts and sits only 250 feet away from residences off Tice Creek Drive. An acoustic blanket or other material will be needed on the west side of the proposed courts to mitigate sound and flying golf balls. Parking could be an issue during large events at the Event Center or Dollar Clubhouse. And coordination would be required between the solar and pickleball projects.

Joseph Hahner, who lives on Tice Creek Drive across from the proposed courts, questioned a project that would remove some redwood trees and possibly lower his property’s value, especially because of the noise factor.

“There needs to be a sound study like the one done at Creekside and Buckeye,” he said. “A partial west wall might be better than nothing, but with the other sides wide open, especially the south side, we’ll hear the whacking of pickleball loud and clear.”

All three committee members agreed a sound study would be necessary before moving forward with the Event Center site, though they delayed recommending it until after seeing the cost comparison. They also dismissed the idea of a fully enclosed indoor facility because the footprint would exceed the space in this new location and cost millions of dollars, at a time when they are finalizing a Facilities Master Plan with some big pricetag items.

Only three GRF directors are currently on the committee as it waits for the District A director vacancy to be filled, likely at the May 26 meeting.

Still, the new site answers a call made by many residents during the past year to build pickleball its own facility, rather than adversely impact an existing amenity, club or facility. Those calls were renewed last month when a sound study was conducted at the Buckeye Tennis Courts. (An initial report on that study is expected to come before the Planning Committee next month.)

“The Event Center site, I think, is magnificent,” Walker said. “I hope it pencils out. It certainly warrants our consideration, but let’s make sure we take residents’ concerns into account.”

The Planning Committee also continued work on the Facilities Master Plan, eliminating some wish list items and designating others as belonging in the “pipeline.”

The committee unanimously agreed to recommend to the Board the removal of a shade structure for Peacock Plaza, a children’s playground for Hillside, a new amphitheater for Dollar and walking paths from the master plan. The four items totaled more than $19 million.

The committee also wants the Board to reprioritize the wish list, moving Dollar Clubhouse renovations, a Gateway building replacement, water reclamation, Sportsmen’s Park access and a Hillside Pool building renovation to a “pipeline” list. Remaining on the lesser priority wish list were a lawn bowling shade structure, Hillside building and Mat House renovation, ramp for the Hillside pool and median conversion.

In other news: Matheson said environmental studies have begun for a possible water reclamation project with monthly meetings now set with the City of Walnut Creek to review issues and opportunities. A follow-up meeting for a workshop held last month is scheduled for June with Cactus Court residents.

Plans for Phase II of the Gateway Studios renovations are being finalized, Matheson said. GRF will seek permits in June in hopes of starting construction in late summer or early fall.

Plaster work at Hillside Pool is complete, but Matheson said the pool cannot reopen until it passes a final inspection by the County Department of Environmental Health. That inspection was scheduled for May 25.