Directors delay funds for some big capital projects until next year’s budget

By Sam RichardsStaff writer

In print on pages 1A, 10A and 11A

A white pickup truck drives along a paved road lined with pine trees and a concrete curb.
A stretch of road between Skycrest and Entry 15 on Golden Rain Road has been approved for construction after the GRF Board approved its 2022 capital budget.News photo by Dan Rosenstrauch

Pickleball expansion, street construction on Golden Rain Road, a new roof for the Fitness Center pools and continued renovations of Gateway’s art studios were among the projects approved as part of the 2022 capital budget.

What’s not included is previously approved renovations to the Dollar Clubhouse bathrooms, and– at least for another year, into 2023 – money for an eastern evacuation road connecting Rossmoor and Alamo and funds for resurfacing tennis courts.

The Board made its choices knowing it has $4,499,500 from the GRF Trust Estate Fund to work with on capital projects for 2022. But Board members said early during their five-hour Feb. 8 meeting that they wanted to hold back on spending up to $1 million of that amount, keeping it available for emergencies.

“We may need to keep some dry powder for unknowns,” like a crash in the real estate market that would slash property transfer tax revenues, or damages from a natural disaster, said Board President Dwight Walker. Other Board members agreed.

The Board ultimately put a hold on $822,000 in spending from what started as a $4,566,775 pot from the Trust Estate Fund, which is replenished by the GRF Membership Transfer fees. This Trust Estate Fund is not fed by money Rossmoor residents pay as part of their monthly coupon.

There were 19 projects on a “wish list,” ranked in priority by each Board member, plus two requests for additional funding of two projects approved by the Board in 2021. The nine members’ rankings were then compiled into a composite ranking list reflecting how the Board in total prioritized each of the 19 proposed 2022 projects. For the 2021 projects, the Board agreed to fund the $10,000 more needed for the Facilities Master Plan, but it rejected the $25,000 extra for the Dollar restrooms.

Secretary Leanne Hamaji pointed out that the Planning Committee had suggested moving the entire Dollar restroom project to the Facilities Master Plan, which is still being reviewed. Because the restroom project was not yet underway, the Board unanimously voted to remove the $100,000 initially approved last year, freeing up more capital funds for the 2022 list.

Directors showed strong verbal support for turning an existing fire road into a full-fledged emergency evacuation route, but they left the $500,000 request off the 2022 capital projects list. The main sticking point, Walker said, is that neither GRF nor the Contra Costa County Fire Protection District has obtained an easement from landowner Discovery Builders Inc. (a Seeno company) to use that land for any purpose. Committing to that work when an easement isn’t yet in hand, Walker and others said, isn’t the best use of that money. The Board signaled it should be part of the 2023 approved funds, even though the existing directors don’t have the authority to guarantee that it is included next year, when new board members will be seated.

Wooden benches and a metal frame stand beside the Bocce Ball courts at Sportsmen's Park.
The Bocce Ball courts at Sportsmen’s Park will see upgrades this year after the GRF Board approved its 2022 capital budget.News photo by Dan Rosenstrauch

As for the resurfacing of the tennis courts at Buckeye, the $100,000 for that work also was moved to the 2023 capital projects list. Though the idea was mentioned that delaying the work is tantamount to deferred maintenance, it was also established that not doing the work immediately would not affect tennis play.

Among the projects approved for funding, the largest single capital project expenditure approved on Feb. 8 was pickleball expansion, at $1.2 million. GRF Resident Services Manager Jeff Matheson said that amount could change substantially depending on which of the various plans under consideration for the expansion is ultimately chosen.

A plan to convert at least one lawn bowling green at Hillside to pickleball courts, described as likely the most expensive option, was made moot when the Board voted 5-4 to remove that site from further consideration as a pickleball expansion possibility.

Another expenditure approved after much discussion was $232,775 for the next phase of a study to build a water reclamation plant. The plant’s primary use would be to irrigate the golf courses, not only to benefit golfers but to provide a massive firebreak in the middle of Rossmoor.

The funding approved is targeted to pay for completion of an environmental impact report, preparation of the request for proposals from prospective design builders and preparation of contract documents.

While Walker and Board member Carl Brown said they favored taking a longer look at the project, its price tag and alternatives, Board members Mary Hurt and Paul Moderacki said it’s better to keep moving forward. Water will only become scarcer and more expensive “This is not about saving money; it’s about having a golf course,” Hurt said. And Moderacki added, “To put a pause on it … we will have lost the momentum we’ve built up so far.”

The approved capital project expenditures, with approximate dollar cost figures, are:

• Phase II of pickleball expansion – $1.2 million • Phase II of the Gateway studio renovations – $950,000 • Street pavement construction at Skycrest and Golden Rain Roads – $570,000 • New roof at the Fitness Center (Tice Creek) pools – $250,000 • Next phase of a study to build a water reclamation plant – $232,775 • Phase II of an access control system (new access control system at the Fitness Center and Golf Center, and new RFID “Smart” identification cards for the community) – $145,000 • Liner for the golf course pond to help eliminate leakage – $125,000 • An alternate transfer pump and piping, to collect runoff water from the surrounding hills before it reaches Tice Creek – $115,000 • MOD office facility improvements – $87,000 • Phase II of the conversion of Rossmoor street medians from approximately 19,500 square feet of lawn to drought-tolerant landscaping – $60,000 • Artificial turf at the bocce courts at Sportsmen’s Park/ Hillside – $55,000 • Golf cart path replacement – $30,000 • Phase II of development of the web portal, adding some enhancements to the golf tee time reservation program, adding a newsletter component where residents can ask for specific updates and making enhancements to the fitness module – $15,000 • Additional funds for the Facilities Master Plan – $10,000 Eliminated from the 2022 capital projects list were the Dollar restrooms, the Alamo evacuation road, replacement of the barbecues and picnic pad at Shady Glen ($30,000), landscaping at Rossmoor Parkway and Golden Rain Road ($40,000), a new California native garden behind the Gateway ceramics and sewing studios ($12,000) and a new seating area for the Farmers Market/food truck area at Gateway ($11,000).