Rossmoor News, December 22, 2021

Bulldozer in action on fire trails

Last month’s storm caused landslides, needed repairs

By Rowena GondenStaff writer

In print on pages 1A and 5A

A yellow excavator with a bulldozer blade works on a dirt slope cut into a grassy hillside beside a road.
A bulldozer stabilizes a hill off Saklan Indian Drive after heavy rains in late October caused the side of the emergency access road to slip down the slope.

Although Rossmoor’s golf courses sustained the most visible damage from the Bay Area’s first major storm of the season, the late October tempest also left its mark elsewhere.

A four-man crew recently finished repairs along a couple of fire trails that heavy rains had left vulnerable to erosion after causing sections of grassy hillside just below the edges of the roads to separate and slide.

The trails themselves remained intact but very likely would have been damaged without intervention, said Trust Maintenance Manager Martijn Lemmens.

Two washouts occurred along the side of an emergency access road off Terra Granada Drive near Grey Eagle Drive; the third and largest bordered a fire trail off Saklan Indian Drive, he said.

Initial estimates pegged the length and cost of the restoration work at four days and $15,000 to $18,000, but the project turned out to be significantly larger.

The paving and grading contractor hired to do the work had to rent a bulldozer for a couple of days to tackle the Saklan site, Lemmens said.

A washed-out hillside with exposed soil and a fence along the edge of a slope.
Damage is seen to a hillside off Saklan Indian Drive from the October storm.

The earthmoving equipment first scooped out the loose soil so the company could assess the actual scope of the problem. The bulldozer then replaced the dirt in layers, compacting each before adding another to ensure the soil’s stability.

Rossmoor’s landscape department placed jute netting over the swaths of exposed soil, a temporary measure to protect the area as vegetation grows back, Lemmens said.

“It’s a lot of work,” he said. In the end, workers spent six days stabilizing the trails at a cost of around $27,000.

The good news is that unspent funds in the budgets for street striping as well as open space and sidewalk maintenance will cover the entire tab with money left over, he said.

And following another round of heavy rain last week, there’s even better news: Although a county rain gauge near Rossmoor showed that the storm dumped nearly 4.75 inches on the area in 48 hours, Lemmens says the netting that landscaping crews had placed over the newly restored slopes just before the deluge along with long straw-filled tubes to stabilize the edge of the fire trails did their job.

“Looks like the repairs held up pretty good,” he said.