Third Mutual Solar Committee provides update on potential solar programs

By John SwearingenThird Mutual secretary

In print on pages 9A and 10A

After the feasibility study for the Rossmoor Solar Initiative failed to produce the hoped-for results, the Third Mutual Solar Committee discussed three possible options for moving forward at its Monday, Oct. 11 meeting.

Individual Solar Systems. Owners apply to put solar on their own roofs as they have done in the past. New applications are unlikely to be approved before the benefits of NEM2 expire because the system has to be installed and approved by PG&E before Dec 15.

Shared Solar System by multiple owners in a single building. This is essentially the same as individual solar but with the ability to quickly lock in the NEM2 tariff before the deadline and with one year to install thereafter, and it requires no change to the Mutual’s policies (the right to do this is granted by AB634).

All the owners in a building wishing to participate in a shared solar system contract with the same installer. The owners individually purchase the number of solar panels they individually need for their own energy requirements. When installed, all the panels will be wired together and connected to one new electrical meter – the Generating Account.

The selected installer immediately prepares an Interconnect Agreement (ICA) with PG&E. The ICA locks in the NEM2 tariff for the participating owners.

The ICA is submitted before the NEM2 deadline, typically within 15 days of the contract being signed.

City and MOD approvals are not needed before submitting the ICA.

The installer has 12 months from the ICA being signed to obtain all necessary city and MOD approvals and install the system.

The installer bills individual owners at the time of installation according to the terms in the contract.

After the system is installed, the generated solar power from all the solar panels is fed back to PG&E via the one meter on a Generating Account.

PG&E credits the individual participating owner accounts for the generated power. The total monthly credit is split by the owners in proportion to the number of panels installed by each owner.

Non-participating owners in this building will in the future still be able to install solar on this building, though the best solar space may have already been taken by the shared solar and other individual installations. However, such future owner will not qualify for the very favorable NEM2 rates – so it is unlikely that many such owners will want to install solar.

Shared Solar System alternative for owners in buildings with only one participant or with roofs not suitable for solar.

This is the successful solution implemented by Mutual 48 several years ago. This does require changes to the Mutual’s policies.

Both buildings must be in the same project or a contiguous Mutual 3 project.

Owners wishing to participate in a shared solar system in a building other than their own must contract with the same installer chosen by that building’s participants.

The contracts all must be signed at the same time (within a day or two). The installer obtains the ICA in the same manner at the same time.

The panels purchased by the owner(s) from different buildings are installed on the shared solar building and connected to the Generating Account meter.

The credits for the energy generated are distributed to the various owners in exactly the same way as in option 2.

The primary difference from option 2 is that some of the roof space is now occupied by an owner who is not a resident in the shared solar building.