GRF Planning Committee Expert advice wanted for restrooms, disability issues
GRF Planning Committee Expert advice wanted for restrooms, disability issues
By Ann PetersonManaging editor

The Planning Committee suggested calling in the experts before making changes to the Dollar Clubhouse restrooms or forming a new task force to tackle disabilities issues in Rossmoor.
With the GRF Board having already approved funds to renovate Dollar’s first-floor restrooms, the Planning Committee debated at its Nov. 15 meeting whether to spend $120,000 to make the restrooms look similar to those renovated last year at Hillside.
The Dollar renovation would not include structural changes but focus more on aesthetic updates, including new tile flooring, fixtures, sinks, lighting, partitions and doors. A unisex restroom already meets ADA requirements, so more expensive structural changes are not needed.
Committee member Kathleen Stumpfel didn’t like the idea of copying Hillside’s look with laminate countertops and other standard finishes for the former Stanley Dollar house.
“It’s OK for a standard restroom, but it’s not quite appropriate for a turn-of-the-century building,” Stumpfel said. “Could we do something that possibly looks a little more modern but also is more suitable for a historic building?”
Committee members Ted Bentley and Paul Moderacki also wondered whether the project should be folded into a larger ADA upgrade for Dollar, which is currently a high priority in the still-under-development Facilities Master Plan.
“I don’t want to Band-Aid this,” Bentley said. “We know the Dollar house needs attention in a number of areas. It would be nice when we’re all done if the bathrooms are up to the standard of the other updates we make.”
CEO Tim O’Keefe drew the committee to a consensus after reminding it of the objections raised when the Dollar picnic grounds were considered for possible pickleball courts. He noted that many residents were concerned that the Board wasn’t respecting the history of the clubhouse.
“If we’re talking about renovation and improvement and enhancement in Dollar, you’ll raise a lot of ire from the same people who objected to pickleball if you don’t have an architect who understands the history,” O’Keefe said. “You want someone who understands what can be done to keep the historical nature of the building.”
Committee Chair Leanne Hamaji suggested it hire a designer, rather than an architect, with historical expertise. The committee unanimously agreed.
Along a similar line, the committee also thought a consultant is needed to assess accessibility issues and ADA improvements in Rossmoor.

The idea started last month in the Policy Committee when a resident suggested creating a task force to better educate the GRF on ways to help disabled residents. Because ADA requirements were tied closely to buildings and amenities, the Policy Committee drafted a charter for a task force focused on disabilities issues and then referred the idea to the Planning Committee because it seemed to tie into its Facilities Master Plan project.
Director of Resident Services Jeff Matheson recommended hiring a consultant, rather than relying on a task force. He explained that a consultant could help inform the committee and Board about what was required by code vs. what would be helpful as it made improvements.
“It takes a little of the emotion out of it,” Matheson explained. “ADA is extremely complicated, and it’s not always clear in the code what is required because we’re private. It’s different than if we were a city.”
The idea held appeal with the committee because it could mirror what consultants have done with the Facilities Master Plan, such as holding town halls open to the community at large.
“Residents could come and contribute feedback,” Hamaji said. “My goal would be to have as much input as possible.”
The committee decided to shelve a task force for now and have staff acquire proposals for consultants who can assess accessibility issues with the amenities, facilities and services in Rossmoor.
In other news from the meeting:
• Matheson noted that completion of the first phase of the Gateway studios renovations remains delayed because of cabinets and exterior doors. Matheson said temporary doors likely will be used until the permanent doors arrive.
• Consultants will hold another town hall for residents to discuss the Facilities Master Plan on Tuesday, Dec. 14, at 1 p.m. in the Event Center.
• GRF submitted the three internal options for possible pickleball courts (Creekside, Hillside and Buckeye) to the Walnut Creek project review team. It expects to receive feedback in the next week or so. Staff also sent a letter expressing interest in exploring a shared facility with Walnut Creek. Matheson said the city indicated it would review the idea with its staff.
• The Planning Committee has recommended that the Board use the same process as previous years to prioritize capital projects and the machinery equipment budget. Unlike in past years, the Board will review these in January instead of December.