Pickleball expansion cost could more than double
By Cathy TallynStaff writer

The cost to improve and expand the Creekside pickleball courts has more than doubled from the $300,000 already approved. And, if a block of Rossmoor Parkway is reconfigured for on-street parking, the cost would nearly quadruple to $1.1 million.
The Planning Committee wants the Finance Committee to determine if the GRF has enough money before it recommends to the GRF Board what the scope and cost of Phase 1 should look like. The Board directors on the Planning Committee have asked Finance to look at the court and parking costs separately.
The four-member Planning Committee spent about 1 1/2 hours on the money matter Thursday. Discussion ranged from why the costs have ballooned to taking potshots at Rossmoor staff and their work.
Resident Services Director Jeff Matheson asked the committee to keep in mind that there’s nowhere else to put the pickleball courts and that Rossmoor spent even more money on facilities for clubs with far fewer members than the 400 in the Pickleball Club, which continues to add members.
Matheson explained that without stabilizing the soil before reconfiguring the courts, they would crack within a few years. Without a better, more expensive sound barrier, the increased noise from three to seven courts would disrupt nearby neighbors. Those costs and a few others add another $450,000 on the original estimate.
An additional $350,000 would be needed to take out the median between Saklan Indian and Stanley Dollar drives to provide additional parking because of already heavy use of the Creekside complex for meetings, dining, golf and pickleball, as well as programs at the nearby Event Center and Dollar Clubhouse, Matheson said.
Director Carl Brown said he has a cheaper plan to eliminate one lane of Rossmoor Parkway to make room for parking. He also criticized staff reports and questioned why professionals are hired to do studies. For example, he said, Rossmoor spent $275,000 on a broadband study, which he criticized using a profanity.
Chairwoman Leanne Hamaji interrupted Brown and asked him not to use vulgar language. CEO Tim O’Keefe added, “To insult staff doesn’t get us anywhere.” Rossmoor hires licensed consultants who put their reputations behind their work, he said.

Matheson explained that the $1.1 million for a complete pickleball project is in line with what GRF spent to add two courts and a social area to the Buckeye tennis complex ($1.6 million), build the table tennis complex at Hillside ($1.5 million) and will spend to renovate one wing of the Gateway hobby studios ($800,000.)
New studies showed that the unexpected need to stabilize the soil under the courts and for a much better noise-absorbing barrier, among other things, would add $450,000.
Committee member Ted Bentley said he thought parking should be considered as part of Phase 2, once the need for parking could be better assessed. “This project is about pickleball courts and what we need to do to get people on the courts,” he said.
Hamaji suggested and the three other committee members agreed to refer the pickleball court cost matter to the Finance Committee.
In other action, the committee decided a request for bicycle safety signs in roadways should be part of a community-wide safety study, of which there are no plans yet.
It also didn’t support a request by Rossmoor churches and service clubs to add information signs at Rossmoor’s entrance. Committee members were concerned about the criteria to be included on the signs, maintaining accurate information and about the signs’ continued maintenance.
The committee was given artist renderings that show where solar panels will be added at Gateway and the Event Center to save on energy costs. The nearby neighborhoods and residents at large will receive the information in the coming weeks, Matheson said.