Solar expansion earns green light
GRF Board approves construction of second phase
By Cathy TallynStaff writer

Solar energy will eventually power all of GRF’s facilities, leaving just a fraction of its needed electricity to be purchased from a power company.
Under a plan adopted by the GRF Board on Jan. 28, solar systems will be installed at Gateway and the Event Center, which will power those facilities as well as the Hillside complex.
GRF already powers its other facilities from energy produced by a large solar farm at Mutual Operations (MOD). This second phase will complete the conversion to solar and produce an estimated 85% to 90% of all the power GRF needs.
Next phase construction costs are estimated at $2.4 million and will be financed through a 10-year lease option plan. After 10 years, GRF can refinance the remaining balance or purchase the system. GRF money that would have been spent on electricity costs will be used to make the lease payments.
“You are saving more than you will pay on the lease,” consultant Jeff Parr of Solar Technologies told the Board.
The Board was presented various options on solar projects, depending on which common areas would receive solar power.
The Board followed the recommendation of the Finance Committee and decided on the most encompassing, but expensive, plan.
Some Board members were concerned about where solar panels would be installed and their effect on neighbors.
Plans now call for cantilever canopies, similar to those installed on The Waterford on Golden Rain Road, to cover most of Gateway’s front parking lot and some of the Event Center’s parking lot in addition to that facility’s roof.
Board member Carl Brown wanted to know why Gateway’s back parking lot won’t have some solar panels so that there would be fewer in the front lot. It’s cheaper to do it on just the front lot, Parr said “I don’t see anything about resident input,” Director Dwight Walker said. “I’d be concerned with the residents who will see the roofs.”
“You will definitely see them,” Parr said. There is a slight chance some light will reflect off the panels, he said.
Resident Services Manager Jeff Matheson said detailed renderings will be made and shown to residents for their comments.
Board member Kathleen Stumpfel said she doesn’t foresee any problems with the aesthetics of the canopies. And, Director Dale Harrington said the canopies would provide shade for cars and residents during the hot summer months.
There was some concern about proposed changes in the Net Energy Metering (NEM) tariff structure that could reduce GRF’s savings by 30% to 50%, eliminate positive cash flow from financing in the initial years and eliminate $2 million to $3 million in savings over the 25-year life of the panels. (The estimated savings over the lifetime of the system is $6.5 million.)
Parr recommended that GRF submit its interconnection application before November so that it is grandfathered into the current lower rate. He said his company would refund the money GRF pays for plans, if GRF can’t get the lower rate.
It’s estimated to take 60 weeks for design, permitting and construction of the solar arrays.
In other action, the Board approved spending $560,000 for paving, machinery and equipment in 2021. The Board decided to hold off for a while on $600,000 in capital projects held over from last year.
That was because of finance concerns due to the loss of some $56,000 a month in rent from John Muir Health for the lease of GRF’s medical building on Rossmoor Parkway.
The projects included two vehicle purchases, development of a facilities masterplan, a median upgrade, renovation of the Dollar Clubhouse restrooms and renovation to and expansion of the pickleball courts at Creekside. Earlier in the meeting, the Board had approved $150,000 for a masterplan.
At Walker’s insistence, the Board gave the go-ahead to spend $30,000 on pickleball court renovation plans.
The delays could last until May when more financial information should be available, CFO Rick Chakoff said.