Renovated restrooms await Hillside’s reopening
By Cathy TallynStaff writer

When Hillside Clubhouse eventually reopens, residents will find that the 1960s-era restrooms have been completely redone to meet today’s needs.
Work began at the end of May and should be finished by the end of the month, Resident Services Director Jeff Matheson said.
It has taken this long because materials are in short supply, he said. With the clubhouse closed because of the coronavirus pandemic, Matheson said there was no need to expedite the project.
Plans call for the complete renovation and enlargement of the restrooms in the lobby of the Diablo Room. The men’s and women’s restrooms located between the Las Trampas and Vista rooms will also be redone and converted to single-occupancy unisex restrooms.
The facilities will comply with the Americans with Disabilities Act (ADA), Matheson said.
When Hillside was built in the 1960s, there were no ADA requirements, he said. The clubhouse has undergone only minor renovations over the years, and thus the restrooms were never required to be brought up to current code, he said. There are no plans to renovate the rest of the complex any time soon, he said.
A resident who was unable to use the Hillside restrooms asked for them to be made handicap accessible.
The GRF Board approved spending up to $312,000 on the renovation, which will come in on budget, Matheson said. The money will come from the Trust Estate Fund.
Three porta potties are set up in the clubhouse parking lot next to the bus shelter for Hillside visitors.
“It was certainly a benefit to have the facility closed so work could proceed without interruption,” Matheson said.
The project was expected to start at the end of March or in early April. There is no telling when the clubhouse will reopen.