It has been stressful having remodeling next door during the shelter-in-place orders. Construction was allowed during the height of the pandemic if the owners were waiting for their units to be habitable.

Remodeling next to me has continued unabated and is in the eighth month. During shelter-in-place I have spent most of my time in my den, which is farthest away from the noise. I also purchased earplugs and landscaping ear covers.

Seniors purchasing today expect to have washers and dryers, step-in-showers, decent-sized refrigerators and, for some, separate half-baths and double-paned windows. This has led to units being purchased by realtors in conjunction with high-end contractors. I call this the gentle gentrification of Rossmoor. And although Rossmoor is still a bargain compared to costs of homes around us, remodeled units are a stretch for many retirees.

I am for the cooperatives being brought up to date, especially the replacement of the old, leaky single-paned windows, which increase energy consumption. I hope that, at some point, grants become available to help residents replace their windows. We have enormous transfer fees in Rossmoor. Why not use some of that money for grants that would actually serve the needs of residents. Residents in coops are also facing the expense of replacing the old pipes in bathroom walls that are leaking and causing dry rot.

I have learned that what residents object to most is the length of time remodels take. I recently interviewed the owner of a local, successful construction company. I learned it is reasonable to expect demo and substantial construction (heavy, noisy work) to be completed on a full remodel in six months or less. I have spoken with residents that have had to tolerate remodeling for as long as a year. Residents have complained how contractors do not hire enough workers dedicated to the job. Sometimes laborers disappear to other jobs for weeks.

Companies should be required to give neighbors a letter with contact information. MOD should collect a copy of the letter. The letter should contain a brief summary of the work, a genuine estimate as to its length, and assurance that they will let the residents know when unusually noisy days will occur, for example, when demo and jack-hammering will take place.

I recommend recording when the project begins and ends and the dates when nothing is being done for weeks at a time. Carpenters are not allowed to play a radio, smoke or leave trash in our dumpsters. Neither are they allowed to work beyond the end of the workday stipulated by MOD. If residents complain about lapses in the rules, they should write down who they spoke to and what was said. Always follow up with a letter to the company.

Contractors are responsible for cleaning up neighboring property and repairing any damages they cause. If construction dust settles all over the windows, patio and furniture, take pictures and ask the supervisor what they plan to do about it and write a follow-up letter. Include photographs. If a resident is unable to obtain their information, call the Walnut Creek Building Department. In most cases they will tell you who pulled the permit. Or you can search the property address or company name on sites like Build Zoom for the company owner and phone number.

Finally, write a letter to MOD about a contractor that took an unusually long time to complete work or didn’t follow the rules. MOD can remove a contractor from the Contractors List provided by the Alterations Department if enough complaints are registered about a contractor.

Patricia Teschner can be emailed at eastbaypjt@gmail.com.