Rossmoor News, August 7, 2019

Will creek restoration begin in 2019?

Permitting agencies visit Rossmoor to see erosion near pickleball courts, Tice Creek

By Maggie SharpeStaff writer

In print on pages 1A and 10A

Dayne Johnson of BKF Engineers, in the center, speaks to a group of visitors standing on a dirt slope beside a road next to Tice Creek Drive.
Dayne Johnson of BKF Engineers, center, speaks with a group of visitors from different government agencies about the creek restoration adjacent to Tice Creek Drive.News photo by Dan Rosenstrauch

Money has been earmarked and design work is done. So why the delay in fixing potentially hazardous erosion at Creekside pickleball courts and the big hole by the sidewalk on Tice Creek Drive, near Buckeye Grove?

“Since repair work involves the creek, we have to get permits from four separate agencies – U.S. Fish and Wildlife, California Fish and Wildlife, the U.S. Corps of Engineers, and the San Francisco Bay Regional Water Quality Control Board,” said Clayton Clark, GRF’s building maintenance manager, adding that residents wonder why the work hasn’t started yet.

“I want to make sure the community knows that it’s not a simple project when we’re dealing with the creek,” said Clark.

To help push the project forward, Sadie McGarvey with Johnson Marigot Consulting took representatives from these agencies on a tour of the two areas in question last week. The consultants are helping facilitate the permitting process for Golden Rain Foundation.

“Workers will be hand-removing the weeds and vegetation so they can look out for native species,” McGarvey told the visiting reps, as they inspected the big, crescent-shaped hole on Tice Creek Drive. “And there will be a biologist on site to monitor native species.”

Dayne Johnson with BRF Engineers in Walnut Creek, GRF’s design consultants for the job, joined the tour and explained the need for repairs to be done as soon as possible.

“Both sites are important, but the erosion on Tice Creek Drive is very close to the sidewalk where residents walk, so it’s more of a safety issue,” said Johnson. “The goal is to do both projects at the same time and get this buttoned up.”

Cassie Schlosser with U.S. Fish and Wildlife said her job was to look for potential environmental hazards that might arise from the repair work.

“We want to make sure there are no adverse effects from the work on wildlife or endangered species,” said Schlosser, citing the California red-legged frog and the Alameda whipsnake as two species on the endangered list.

Leif Goude, Cassie Schlosser and Sadie McGarvey stand and kneel on a wooded creek bank among exposed roots.
Leif Goude, left, and Cassie Schlosser, right, both from the U.S. Dept. of Fish and Wildlife, speak with Sadie McGarvey, with Johnson Marigot Consulting, about the creek restoration project at the Creekside pickleball courts.News photo by Dan Rosenstrauch

Clark hopes getting all the reps together will speed things up. “Once they see the impact on the sidewalk near Buckeye Grove and the threat to the pickleball courts, it might streamline the permit process and get the project moving,” said Clark, adding that GRF has a “drop dead date of Sept. 3 to get the work started.” Naomi Schowalter, an ecologist with the Army Corps of Engineers, said timing depends on whether there’s an “informal” or “formal” consultation process. In an “informal” process, GRF could get the green light to start work as early as mid- to late-August.

Clark said the next step is to finalize design specs for the work, based on feedback from the visiting agencies.

Repair work

The repair work, estimated at about $1 million, was prioritized by the GRF Board as part of its 2019 capital projects.

“Technically, this is an emergency repair job,” said project engineer Johnson. “Erosion and scouring of the banks are undermining the pickleball courts and the sidewalk on Tice Creek Drive.”

The same approach will be used to fix both sites, said Johnson. Work involves excavating the site, building “steps” on the bank, installing riprap (basically big stones), filling in behind the stones, and planting willow stakes – which are notoriously fast growers.

Clark said residents will be alerted before the work begins.

“We plan to let the pickleball players know when construction is going to start and finish, as they won’t be able to play on the Creekside courts while work is going on,” said Clark, adding that work on the Creekside pickleball embankment could take about two or three weeks.