Rossmoor News, April 17, 2019

Solar farms are closer to reality

By Cathy TallynStaff writer

In print on pages 1A and 3A

Keep your fingers crossed, but it looks like construction of the solar arrays at Mutual Operations (MOD) off of Rockview Drive will begin by the end of the month.

All but one of the necessary permits from governmental agencies have been granted. That just leaves a building permit from the city of Walnut Creek.

“Assuming no endangered or protected species are identified and assuming the building permit is issued over the next few weeks, we should see construction begin toward the end of April,” said Jeff Matheson, resident services director.

The array won’t cost Rossmoor anything because it’s a power-purchase agreement. As such, the system is constructed and owned by a third party. Rossmoor will not own the system.

The array will save Rossmoor money on its electricity bill. The electricity for GRF’s common facilities is about $600,000 a year.

The solar farms could save Rossmoor $5 to $6 million over the 20-year life of the agreement with NextEra Energy.

Discussions over construction of the solar farms began in 2015. One thing after another has delayed the project.

Last month, it appeared the project might be dead in the water when a new fire regulation would have required cost prohibitive fire sprinklers under the parking lot canopy.

With a redesign, the project has received the necessary permit from the Contra Costa County Fire Protection District.

Plans call for two solar farms. One will be mounted on the hillside and cover 35,000 square feet just below the MOD building complex. There will be nine carport canopies over the RV lot.

The redesigned plans call for carport arrays of no more than 5,000 square feet each with a 10-foot separation.

“With the modifications, the requirement for sprinklers was avoided,” Matheson said.

“The revised plans have now been resubmitted to the city. The city has issued the site development permit and the building permit is pending final review.

“The contractor will be onsite to complete survey work and the required preconstruction biological assessment,” he said.

Both solar farms will be erected at the same time, Matheson said. It’s unknown how long it will take.