Rossmoor News, March 20, 2019

Sprinklers almost derail solar project

Requirement means design must change

By Ann PetersonManaging editor

In print on pages 1A and 11A

The solar farm project at Rossmoor ran into yet another permitting issue this winter, but construction is still expected to start by late spring.

The oft-delayed project hit its most recent snag when a permit was sought from the Contra Costa Fire Protection District.

“The initial code requirements from the fire district say we need sprinklers and that was not planned,” said Jeff Matheson, Resident Services Department director. “It’s a huge additional expense.”

Matheson explained that any structure greater than 5,000 square feet requires sprinklers. The original design for one of the two planned solar arrays called for three carport-like structures of more than 5,000 square feet being built over the RV parking lot behind the Mutual Operations Department.

The sprinkler requirement is a relatively new code – one that Matheson said likely will be amended next year. “But we’re caught in the middle.”

The GRF reached out to County Supervisor Candace Andersen for help in obtaining a variance with the fire district. Inevitably, Matheson said, the project owner suggested the less expensive option of creating a new design, which will put 10 feet of separation between carports of no more than 5,000 square feet each.

Matheson said the fire district has promised to expedite a review of the new design, which then must be submitted to Walnut Creek for review.

Despite the time needed for these reviews, Matheson said, construction for the project still should be underway by late spring.

In addition to the RV lot, solar arrays also will be installed along the hillside off Rockview Drive.

The solar farm project began in 2015 with feasibility discussions. Since then, the project has been beset by permitting issues that have frequently delayed start of construction.