Tech Committee delivers recommendations
Very tough decisions now ahead for GRF Board
By Ann PetersonManaging editor
In print on pages 1A, 7A and 12A

The Ad Hoc Technology Committee left the GRF directors with some tough decisions after unveiling 25 projects as part of a five-year Strategic Technology plan for Rossmoor.
Committee Chairman Fred Kern delivered highlights from the committee’s 63-page report during Tuesday’s GRF Board meeting. The report was the culmination of 18 months of work that involved paring more than 100 ideas into 25 projects and dividing those into categories – highly recommended, recommended, inevitable projects, GRF already funded and parking lot items, the latter of which the committee felt was out of its scope.
Seven projects made the cut for highly recommended: drone technology, fiber optic cable replacement, Gateway data site relocation, LED street lighting, On-Demand transportation trial project, solar system common areas and TV/Internet provider alternatives.
No less important, the inevitable project category was selected because of the committee’s push to make services and amenities more interactive online but also its understanding that such a move can be complex and costly. Among those project ideas were a web-enabled member portal for purchasing tickets and scheduling golf tee times and data integration.
The end result was a highly praised report of ideas meant to bring the GRF more fully into a world of evolving technology.
The hard part is now deciding how to move forward, many board members said.
“You’ve now thrown 25 projects into committee baskets,” said Director Les Birdsall. “And when I see highly recommended and then inevitable, I have to ask – which comes first, inevitable or highly recommended? Those of us who are not tech savvy, we’re going to be asking a lot of you.”
The board also has to balance the potential cost of implementing these projects with needs already on the table, including repairs of Tice Creek alongside the Creekside pickleball courts.
“How do we compare this to the creek restoration, for example?” Birdsall asked. “We have a lot of decisions to make, but we appreciate what you’ve done because without it, we’d have no idea where to even start.”
What comes next?
Kern had a few ideas about the possible next steps.
“Load up on the low-money ones first,” he suggested. “You have some projects that don’t cost anything except some staff time. That’s something to consider.”
Those ideas included the already underway LED street lighting initiative and trying to acquire a two-year grant similar to what Livermore Valley received to subsidize transportation with On- Demand ride sharing and taxi service. (GRF is currently running a trial for On Demand bus service.)
Other low-cost projects include exploring a second solar field site to go along with an already identified first site, which is projected to offset about 60 percent of GRF’s electricity usage. A second site potentially could offset 80 percent of the remaining power.
Addressing top needs
The highly recommended projects also addressed some looming needs, such as replacing the 21-year-old fiber optic cables within the next year or two. Kern passed around samples of the fiber optic cables and explained that some strands have stopped working and at least one conduit, between the Mutual Operations Department and Gateway, appears to be blocked.

He added that the cost estimate for replacing the cables is $225,000 – “if everything goes well” – but without further exploration, there’s no way to know how many blocks might be uncovered, driving up the cost.
Director Mary Neff asked, “If something goes wrong, could it cost a half-million dollars?”
“That’s hard to answer,” Kern said. “But if the whole thing goes down, we’re in deep trouble.”
With the current Comcast contract set to expire in 2021, the committee also suggested forming a committee next year to review options for TV and Internet providers.
And the committee recommended purchasing one or more drones to help with preventive maintenance, landscape management, fire abatement, traffic management, architectural planning and disaster assessment.
“I’m hopeful security might be a potential benefit of this, too, one day,” said Director Steve Roath.
Complex ideas
Kern also detailed at great length the inevitable projects. Topping the priority list is data integration, because GRF currently uses six different databases, and the creation of a secure resident portal, for online access to GRF services, documents and even transactions such as buying tickets.
The committee also recognized the critical question of whether the current Jenark software for Community Association Management can be upgraded to meet Rossmoor’s growing IT needs or if other options need to be explored.
“None of the options is simple,” Kern said. “That could potentially be the most expensive undertaking and have a huge impact for years to come.”
One resident, Dick Bertrand, addressed the board during the Residents’ Forum, to offer his insight from many years serving at the executive level of several software companies. Among his suggestions, Bertrand said, the board should consider time and money savings, ease of use, what has worked before and, above all, the residents and staff who will be the end user of the technology.
“Their voices should dominate the selection process,” Bertrand said, “not the technologist.”
The Technology Committee was comprised of residents Kern, Mary England, Chris Slee, Vickie Swisher, Della Temple, David Vereeke, Heinz Weihrich and ex-officio member Bob Kelso.
Reflecting back on the work done by his committee, Kern called it an “enriching experience” to work with members who had such different backgrounds.
“It was also humbling to see how fast technology has evolved,” he said. “It’s hard to stay up and stay current because it’s constantly changing.”