Rossmoor News, December 26, 2018

Construction of solar farms slated to begin in January

By Cathy TallynStaff writer

In print on pages 1A and 3A

Two utility crews work from cherry pickers on new utility poles along a grassy hillside.
Crews used “cherry pickers” so they could work on new poles for electric lines needed for the solar array.News photos by Mike DiCarlo

Two new solar farms could take shape in Rossmoor as early as next month.

Plans call for solar arrays to be erected on a hillside off Rockview Drive, near the entrance to the Mutual Operations Department (MOD), and over a nearby RV storage lot.

Discussion of the feasibility of solar began in 2015. The project has been stalled due to permitting issues with various government entities.

“We anticipate breaking ground early in the new year,” said Jeff Matheson, resident services director.

Two weeks ago, PG&E erected service poles at MOD for the project.

“The completion date will depend on the weather,”

Matheson said, “but the hope is the facility will be operational in late spring/early summer.”

The array won’t cost Rossmoor anything because it is a power-purchase agreement. With a power-purchase agreement, the system is constructed and owned by a third party. GRF will not own the system.

The array will save Rossmoor money on its electric bill. The electricity cost for GRF’s common facilities is about $600,000 a year.

PG&E trucks and a bucket lift work beside a hillside at Mutual Operations.
PG&E crews worked on installing power poles at Mutual Operations.

“The project should save GRF $5 to $6 million over the 20-year life of the agreement with NextEra Energy,” Matheson said.

About half of the panels will be located across the street from MOD’s recycle center. The hillside panels will be tucked below the knolls and ridges to minimize the visual impact for residents across the valley who can see the site.

The rest of the panels will be erected over the lower RV lot, which wraps around three sides of the building complex.

Some RVs stored at the lot have been moved temporarily to various Rossmoor streets because of the project. How long they will remain on the streets is uncertain. “Everything depends on the weather and how quickly we can get the lot paved and then the RVs moved back,” Matheson said. “It will be a little while.”

It was at the behest of Solar-Powered Rossmoor that the GRF Board took up the solar project. It was originally thought that all the solar panels would be on the hillside. But, soil tests revealed that the hillside is too steep and rocky. There were other delays, as well.

“The project is utilizing a program called NEMA (net energy metering aggregation),”

Matheson said. “The project should offset 50 to 60 percent of energy for the facilities included in the aggregation.

“All the power from the arrays will go into the PG&E grid,” he added. “GRF gets credit for the power going into the grid. That credit should offset the cost of energy GRF uses from the grid.”