Rossmoor News, April 25, 2018

Walnut Creek Planning Commission approves Rossmoor’s solar permit

By Jennifer MuContributing writer

In print on pages 1A and 12A

The Planning Commission for the city of Walnut Creek voted unanimously on April 12 to approve several permits and an environmental review required for Rossmoor’s solar array project.

Several members of Sustainable Rossmoor attended the evening’s public hearing to show support of the project, including the club officers Marcia McLean, Brad Waite, Jim Ware and Carol Weed. All of them spoke at the hearing and answered many Rossmoor-specific questions from the commissioners.

The commissioners had concerns about community outreach activities related to the solar farm project, and also had questions about how the electricity generated by the solar array will be used, and whether the savings will be returned to all Rossmoor residents.

Sustainable Rossmoor’s Vice President Brad Waite, who has worked with the GRF Board and Rossmoor’s administration on this project since its beginning, answered all those questions. Other Sustainable Rossmoor speakers also stressed not only the environmental impact of the solar farm but also the beneficial economic impact for Rossmoor residents.

Several commissioners commended Sustainable Rossmoor members for their devotion to making this project a success. The GRF solar farm project is the first initiative undertaken by Sustainable Rossmoor (formerly named Solar Powered Rossmoor).

It has been three years in the works since club members first approached the GRF Board with the solar farm concept.

The solar project measures 3.18 acres in size, which includes 1,710 ground-mounted photovoltaic (PV) solar panels on a hillside near the Mutual Operations offices on Rockview Drive, and six carport roof structures over the RV parking lot supporting 1,548 PV panels. Because of the size and the location of the project, it has been under the city’s careful scrutiny so it will comply with a web of complicated state and federal laws, as well as city ordinances governing protected trees.

The approved permits include a conditional use permit, tree removal permit and tree drip-line encroachment permit. The commission also approved a Mitigated Negative Declaration (MND) and mitigation monitoring and reporting program recommended by the city’s planning staff.

The MND was required under the California Environment Quality Act because the initial study performed by the planning staff found that the project may have potential impacts on several endangered species that are nesting or roosting on or near the project site. These animals, protected under federal and state laws, include barn owls, bats, Alameda whip snakes and passerines such as jays, juncos, wrens and towhees.

The Planning Commission’s approval allows the project’s developer, NextEra Energy, to move forward with the city’s permitting process with the Building Department. There are mitigation measures the developer must take before a building permit is issued. At the same time, NextEra Energy will begin to work with PG&E on technical issues.