G

RF Board members had a lengthy discussion last Tuesday on capital projects that they would like to work on over the next 12 to 18 months. The Board came up with seven projects totaling $1,535,000, and another project that does not have a cost at this time, which all agreed were the most important to move forward on this year.

“This is a discussion on capital items. We are going to review the potential project list, look at the Trust Fund and start a dialogue,” said GRF Treasurer Mary Neff. “If there is a chance we want to do a project in the next 18 months, we should decide that now. The timeline is driving the discussion.”

Neff explained that the next step would be to refer the list of projects to the GRF Finance Committee for further analysis.

The Tice Creek Fitness Center loan amount was the starting point for the discussion. Mechanics Bank agreed to loan $8 million to remodel the Tice Creek Fitness Center. However, it is estimated that GRF will need to borrow only about $5 million to complete the project, rather than the full $8 million.

The questions before the Board were: Are there capital projects in the next 18 months that will require Trust Estate funds and should GRF borrow more than the minimum needed to finance the Fitness Center to provide a cushion for future anticipated projects?

Resident Services Director Jeff Matheson speaks at a microphone during a Board meeting.
Resident Services Director Jeff Matheson talked to the Board about Gateway studio and Hillside Clubhouse improvements.

The projects that got the thumbs-up for funding in 2018 are as follows in the bullet points:

• Pedestrian traffic safety project at an estimated cost of $75,000 “The GRF Planning Committee has looked at this and decided that the Board needs to work on safety issues around Gateway,” said GRF Director Les Birdsall, who chairs the Planning Committee.

Public Safety Manager Dennis Bell explained that the Board approved four projects that called for reconfigured roadways, pedestrian-activated flashing crosswalks, stop sign lights and the removal and replacement of some crosswalks. He said that he is currently seeking requests for proposals for this work.

• Alternative energy conservation projects at an estimated cost of $250,000

CEO Tim O’Keefe explained that GRF owns more than 400 light standards and is doing a pilot testing of LED lights on some of the light standards in Gateway parking lot. The LED lights use one-10th of the energy of fluorescent and incandescent lightbulbs. “Do you want to replace all of the lights now or over time?” he asked.

“It is definitely something we want to do now as it will save us money,” said Director Carl Brown.

GRF Director Les Birdsall sits at the board table with a laptop and microphone during a meeting.
GRF Director Les BirdsallNews photos by Mike DiCarlo

• Gateway studio improvements at an estimated cost of $200,000 for design

Resident Services Manager Jeff Matheson said that a request for proposal for architectural and design work has been sent to design firms as requested by the Board. “The process will take time,” said Matheson. “If you are looking at construction, it will be in 2019.” • Creek restoration at a cost of $800,000 for design work

Two areas of Tice Creek that are of great concern are near the pickleball courts on Rossmoor Parkway and near the Buckeye tennis courts. Director of Mutual Operations Paul Donner said that he will provide a report on the cost of the repairs.

• Water reclamation facility for watering the golf course with waste water at a cost to be determined

O’Keefe explained that the consultant on the project has completed the preliminary work and that meetings have been held with Walnut Creek and the Sanitary District. He expects a report will be ready to present to the Board by the April meeting.

“This project will be one of the most important things that can be done for the community to preserve the amenity of the golf course,” said O’Keefe. “The golf course