Rossmoor News, March 14, 2018

Waterford solar project moving along

In print on page 9A

Workers on elevated lifts install steel beams for a solar carport over a landscaped parking lot island.
News photo by Mike DiCarloNews photo by Mike DiCarlo

The฀Waterford฀solar฀project,฀located฀in฀its฀parking฀lot฀on฀the฀corner฀of฀Golden฀Rain฀Road฀and฀ Rossmoor฀Parkway,฀is฀moving฀right฀along.฀The฀project฀started฀the฀last฀week฀of฀January฀and฀steel฀ pillars were put in place last week. The project is expected to take a total of eight to nine weeks. When฀completed,฀solar฀panels฀will฀cover฀the฀lot฀and฀is฀expected฀to฀save฀the฀Waterford฀more฀ than฀$6.5฀million฀on฀its฀electric฀bills฀over฀a฀30-year฀period.฀During฀part฀of฀the฀parking฀lot฀closure,฀ some฀Waterford฀and฀Securitas฀employees฀are฀parking฀along฀Tice฀Creek฀and฀Golden฀Rain.