Fitness Center modulars to close Dec. 22

In print on pages 1A and 5A

As the renovation of the Fitness Center nears completion, staff is preparing to close down the temporary modulars in the parking lot and transition to the new center – officially called the Tice Creek Fitness Center.

The modulars will be closed over the holiday season so staff can empty all the contents including equipment, files and accessories. This work will take place from Dec. 23 through Jan. 2. The modular buildings will then need to be disassembled and moved out, which will take 10 working days.

Once the modulars are removed, the parking lot needs to be repaired, which should take two days. Moving the modular buildings and repairing the parking lot will take up most of the available parking. This work cannot be done while the Fitness Center and pools are open.

The Tice Creek Fitness Center will have new equipment, new technology and a new supervisor. Once new equipment is in place, staff will then need time to set up the facility, train on all the new equipment and prepare for an opening. All these steps will take about a month. The new facility is anticipated to open mid to late January.

The pools at Tice Creek (formerly Del Valle) will remain open through the process.