Residents frustrated with pool not opening. How did delay happen?
By Maureen O’RourkeManaging editor

Rossmoor residents have expressed frustration and unhappiness when the Del Valle pool complex was not reopened as promised. After the pools were replastered and the upgrades on the pump room were done, the pool was supposed to open by the Fourth of July. Then that date was pushed back to Labor Day, and then there was another delay to Sept. 18.
But the pool is still not open and residents want to know why. And they want to know when it will be open.
The pool will probably open soon, according to Resident Services Director Jeff Matheson. But he doesn’t want to announce a date until Rossmoor receives final approval from the county. When it does open, if there is no time to announce it in the News, there will be a soft opening and it will be announced on the website and Channel 28.
Matheson explained how Rossmoor got into the predicament with the pool complex.
“We were just going to do the main Fitness Center renovation, which included the locker rooms but no pools,” he said. “All the permits were secured for the main renovation.”
Permits were required from the city of Walnut Creek Building Department, the Fire Protection District and the Sanitary District.
However, when the work was set to start, the contractor indicated that the pool complex would have to close off and on during the work on the Fitness Center.
“At that time, it made sense to do the work on the pools that was scheduled for 2018,” Matheson said. When GRF hired the pool contractors to do the plaster and update the pump room, they were required to get their permits, which were separate from the permits for the renovation of the Fitness Center.
The contractor that plastered the pool received a County Health Department permit. “The contractor said that on this type of work, he only had to get a permit from county health, which he got, and he started the work,” said Matheson. “However, while the city inspector was inspecting the Fitness Center renovation, he indicated that a city permit was needed for the plaster work.”
That is when the city shut down the pool work.
Matheson said that obtaining new permits and new plans took some time. “Then the city came back to us and said that the value of the work was over $150,000, so an Americans With Disabilities Act (ADA) plan was needed for the pool access.”

The permits were obtained and the work was able to start again. However, Rossmoor was working with two government agencies, both offering different opinions.
“We got clearance from the city to open the pool on Sept. 18, including the two new changing rooms off the deck and the four deck showers, but the county came out to do the final the Friday before and told us that the pool couldn’t open because the locker rooms were under renovation, and without them there were insufficient toilets, sinks and showers” he said.
The county said that the occupancy load for the pool enclosure is classified at 375 people, and with that load, there would need to be a designated number of showers, toilets and sinks. Matheson said that once the locker rooms were finished as part of the renovation of the Fitness Center, that designated number would be met. But the plan was to open the pools using two changing rooms off the deck – each with a toilet, sink and shower, as well as four additional showers on the pool deck. The restrooms in the modular in the parking lot were also added into the number of restroom offerings.
“We thought we met the requirements, but the county said we could not use the restrooms in the modular,” Matheson said. “We have been negotiating with the county by showing that the use of the pools never comes close to 375. It’s more like 50 people.”
The county is working with Rossmoor and the city to ensure that the occupancy is lower than allowed. Rossmoor submitted to the county an occupancy plan.
“Now we are waiting for the final inspection from the county,” he said. That inspection should take place this week. “As soon as we get the OK, we will open.”
Matheson explained that if the occupancy hits 60 people – which is not likely – some may be turned away.
“I don’t think it will be an issue at all,” he said.
Another issue that some residents have noted is the concrete sidewalk in front of the building is not finished. This concrete will not be poured for some time. People will need to access the pool through the patio area that faces the parking lot. Once the Fitness Center opens early in 2018, the entrance to the pool will be through the Fitness Center.
After going through all of the issues with the county permit process and the inspections, Matheson is just as frustrated as residents, but understands that Rossmoor has to follow the codes. “The county has to enforce the code, otherwise they are liable,” he said. “And, the code is not flexible.”