Rossmoor News, October 11, 2017

Work nearly complete on golf cart paths

By Maggie SharpeStaff writer

In print on pages 1A and 3A

Workers in yellow safety vests smooth fresh concrete on a section of the golf cart path beside a fairway, with a cart and trees behind them.
Workers repair sections of the path along Creekside Course.News photo by Mike diCarlo

Repair work on the golf cart paths along the nine-hole Creekside Golf Course is currently underway, and should be finished within the next few days, according to Director of Golf Mark Heptig.

“This is year two of a threeyear plan to repair the cart paths around both golf courses,” said Heptig. “Last year we worked on paths around the Dollar Course; this year we’re working exclusively on Creekside paths.”

Heptig said the work – which involves removing and replacing about 6 to 8 feet of path in most of the sections – is a “minor inconvenience.”

“We have the paths taped off where we’re working so you just have to go around the area,” said Heptig, adding that they’re removing about 6,000 square feet of concrete in total.

The budget for the work, which is a Trust Facility and Property Maintenance project – those include such projects as street and sewer line maintenance, as well as open spaces – is between $40,000 and $45,000 each year.

Heptig said that if the paths were only for golf carts, their current state of repair would likely be acceptable. But a lot of people walk along the paths, so they want to make sure that paths are safe.

“A lot of walkers use the paths, especially on Mondays, so we don’t want trips and falls,” said Heptig. “The paths need to be as smooth as possible.”

Heptig said that the workers, from DHR Construction, identify areas that need repair, spray paint an outline of the damage, then jack hammer the area and finally pour in fresh concrete.

While the work is in progress, the areas are taped off to golf cart riders and walkers with yellow cautionary tape.

Heptig added that cracks and fissures in the cart paths are an inevitable part of living in California, where the ground shifts over the years causing little movements that result in cracks in the cement.

“The clay soil also compacts and expands all the time, so eventually that causes little cracks to appear,” said Heptig.

Once the three-year repair plan is complete in 2018, Heptig said the golf course will keep up with normal maintenance of the paths, which comes out of the golf course budget, to the tune of roughly $1,000 per year.