GRF 2018 budget hearing held over two days with Board, Finance Committee
Proposed budget has $14 monthly increase per manor
By Maureen O’RourkeManaging editor

The 2018 GRF budget season has arrived. The GRF Board and the Finance Committee held a review of the proposed 2018 budget before a sparse audience at two meetings last Tuesday and Wednesday.
It took more than six hours over the two days for the Board, the committee and GRF staff to go over the 130-page budget covering 16 departments, new programs and program augmentation and modifications, the costs of the pension plan and a budget for maintenance projects.
What comes out of these meetings is the basis for the 2018 coupon for the GRF side of the budget. The coupon is the monthly fee that residents pay for all departments and services that are under GRF. The Mutual coupon is developed separately by each Mutual board and that is added to the GRF coupon.
The departments in the GRF budget include Executive Services, Legal and Human Resources, Public Safety/ Securitas, Bus Transportation, Counseling, Accounting/Information Technology, the Handyman Service, Recreation, Aquatics, the Fitness Center, Golf/Lawn Bowling and the Pro Shop, Facilities Maintenance, Vehicle Maintenance (including buses), Landscape Maintenance (of Trust properties), Custodial Service and Communications (the News, Channel 28 and the websites).

The 2018 coupon
The initial draft of the budget has the coupon increasing from $260.33 in 2017 to $274.60 in 2018. This total includes cable TV and Internet service in the amount of $56.87, which is a contractual increase. (However, the increase has not yet been confirmed by Comcast, so this figure can change.)
In addition, if the Board approves new program augmentations, such as the hiring of a landscape technician, a recycle consultant, front desk staff for the Fitness Center, a new Fitness Center specialist and one golf course position, then the coupon could potentially increase another $4.44 per manor per month.
There may also be some reductions in the proposed budget, thus reducing the coupon, including an estimated $49,000 for health insurance and an unknown amount for electricity savings when the solar farm goes on line by July 2018. The Finance Committee will discuss the budget again at its meeting on Tuesday, Sept. 26, at 9 a.m. in the Board Room, and will present its recommendations to the GRF Board at its meeting on Thursday, Sept. 28, at 9 a.m. in Peacock Hall at Gateway. The Board will vote on the final budget and have a 2018 coupon amount at that meeting.
Staff worked on keeping costs down

Day one of the budget meeting covered department budgets, most of which have been kept flat. In introducing the budget, CEO Tim O’Keefe said that despite budgeting a 15 percent increase in health insurance costs, a 9 percent increase in water costs and a 3.8 percent increase in wages, “the overall GRF operations and Trust facility budgets were held to a most 3.3 percent overall increase.”
However, without an operating surplus to carry over into 2018 to help reduce the coupon increase, the net budget impact results in a 6 percent increase in the coupon before cable TV/ broadband.
O’Keefe said that GRF staff has been judicious in preparing the budget to keep costs as low as possible, holding the line on many expenses, but that the Trust facility/property maintenance portion of the budget has a 38.6 percent increase, primarily due to the need for critical asset management.
“For many years, the coupon rate increases have been below the rate of inflation and when this happens, there is deferred maintenance,” he said. “This catches up with us and it will in 2018.” He said that some items in the Trust maintenance budget could be deferred, but that “preservation of the amenities and assets is paramount,” he said. “I encourage the Board to do their best to preserve the Trust assets.”

Department budgets
Notable changes in the department budgets include the following:
• Public Safety: The Securitas contract will increase $20,068 (1.6 percent) in 2018.
• Bus Transportation: Some restructuring of staff has taken place, adding .35 employee hours, from 11.15 to 11.50.
• Recreation: The projected revenue for Excursions has dropped $30,000, while the ticketed events revenue has been projected to increase by $75,000. Additional revenue of $10,000 has been projected for the several shred days held throughout the year.

• Fitness: Personal training revenue is projected to increase by $30,000. The supplies budget is projected to decrease by $16,000 because the new Fitness Center will have a vast majority of new equipment and a majority of it will be new in 2018.
• Golf Course: With resident fee increases recommended for 2018, an additional income of $20,000 is expected. Increasing the annual card could also bring in $20,000 additional income.
• Communications: Increase projected in bus advertising revenue by $10,000. The News advertising revenue expected to remain the same.
Day two–staff proposals

Day two of the budget meetings started out with recommendations for adding 4.5 staff positions plus a recycle consultant in 2018 at a cost for salary and benefits of $356,000.
The requested positions are a landscape technician for Trust properties, a recycle consultant (not a permanent position), front desk staff for the Fitness Center (1.5), a new fitness specialist for the Fitness Center and one golf course staff position.
Mutual Operations Director Paul Donner explained that with the addition of the Event Center, the dog park, the table tennis facility, the bocce courts, the median outside the gate, added color spots and more than six miles of hiking trails to the Trust amenities over the years, additional staff has not been added to accommodate the increased workload. “We have become thin in the Landscape Department,” he said.
An additional position is needed to prevent letting the state of Rossmoor’s amenities depreciate as a result of the additional workload.
Della Temple of the Finance Committee asked what would happen if this position was not added.

“We would continue to do the best we can with what we have,” Donner said. “There are times we don’t get things done quickly enough, or there may be a broken sprinkler we are not aware of.”
Recycle consultant
Donner also recommended that GRF enter into a sixmonth agreement with a recycle consultant at a cost of $60,000 to develop a complete comprehensive recycle plan that would be designed and implemented specifically for Rossmoor. The agreement would include 30 days of onsite training for the landscape manager and other key Rossmoor staff.
The cost does not include