CEO’s Report
Fitness Center Renovation and Del Valle pool updates
By Tim O’Keefe, CEO
The Fitness Center renovation project is still proceeding on time and on budget with a reopening of the facility scheduled for January 2018. If residents are interested in watching a series of time-lapse videos of the demolition and construction, visit www.rossmoorfitness.com and click on the video in the middle of the page above the heading “What It Looks Like Now” (earlier videos are included in links near the bottom of the page).
For the space planner’s digitized rendering of the downstairs equipment layout, scroll a little further down the page and click the video under the heading “What’s Coming in the Future.” The rendering walks the viewer through the equipment layout on the main floor and provides an excellent initial view of the main renovated space. It also depicts the ground floor windows which will eliminate the claustrophobic feeling of the old space. However, it does not show the addition of the upstairs clerestory windows, the gym, the training rooms or the interior paint colors which will add additional light, functionality and aesthetics.
Del Valle pool update
The Del Valle pools are in the process of being re-plastered and being brought up to the current standards of the Americans with Disabilities Act. After some city-imposed delays, work on the pools has re-started. Safety improvements include an upgraded fire alarm system, improved handrails, new chair lift and re-graded decks.
The pumps and heaters are being replaced and a new ultra-violet water treatment system has been added. There will also be new accessible restrooms and showers on the pool deck. The exterior sidewalk, stairway and handicap parking are also being modified to improve accessibility. It is expected that the work will be completed by mid-September. Thanks to everyone for their patience!
Solar farm update
Many residents have inquired as to the status of the GRF solar farm. The plans are under review by the city. It was originally reported that construction would commence in the fall with completion by the end of the year. While that is still possible, the city’s design modifications make that unlikely. Once the permits are received, construction will take three to six months, depending on the weather. GRF now expects that the project will be completed in the first half of 2018.
For those new to the community, GRF executed a solar power purchase agreement with a third party for the installation of a 1 megawatt solar farm in Rossmoor. The third party will design and own the system and GRF willguarantee the purchase of 100 percent of the power the system generates. Solar panels will be installed on a Rockview hillside and on canopies that will be placed above the RV parking lot.
It is expected that approximately 60 percent of GRF’s electricity will be generated by the solar system saving about $6 million over the 25 years of the agreement. The advantage of a power purchase agreement is that GRF does not have to invest any capital in the project, saving the community millions of dollars. More information on this project to come.
Drop creek structure replacement
Work continues near the front gate on the drop structure in the creek. A drop structure is used to control the flow of water down the creek to minimize erosion and maximize the habitability of creek vegetation, fish and other animals.
The old concrete structure had failed and deteriorated to such an extent that, if left untended, could pose hazards to the stability of Rossmoor Parkway and the Waterford buildings. The heavy rains this winter accelerated the erosion. After more than two years of navigating the permitting process with various regulatory agencies including the Army Corps of Engineers, the federal and state Departments of Fish and Wildlife, the city of Walnut Creek and the California Water Resources Board, the permits were finally issued and the work quickly commenced since the permit requires that all work be completed no later than Oct. 15, prior to the rainy season. A biologist is onsite every day to ensure that the work meets all regulatory and environmental requirements.
The construction work requires the closure of the last entrance lane on the right at the gate, as well as the west sidewalk from Golden Rain Road to the crosswalk at St. Anne’s Church. It also requires the temporary diversion of the creek and the removal of nearly two dozen trees; however, twice as many trees will be planted prior to completion. The installation will also include 300 tons of new stone weirs that will allow the creek to “drop” to a lower elevation and reduce erosion. Thanks to everyone for their patience while this important work is completed.
Fireside Room upgrades
The Fireside Room at Gateway will receive some much-needed upgrades to the audio/visual equipment. The sound system will be upgraded to digital quality, the screen will descend to within 5.0 feet of the floor and the projector will be replaced with HD quality resolution and higher lumens for better light quality. In addition, the wiring and connections will be replaced which should eliminate the problems of periodic dropped audio and visual signals.
This work will be done in the Fireside Room between Sept. 25 and 29. With the addition of the blackout shades last spring, event attendees will have a much-improved experience at future Fireside events when all the work is complete.
Employee transition
Five employees commenced employment with the Golden Rain Foundation in July: Jasmine Hajyan-Quigley, LCSW, Counseling Services; Isaac Torres, carpenter, Building Maintenance; Kelly Mattison, Board Services coordinator, Board Office; Zacary Henry, range worker, Golf Pro Shop; and Mellissa Fortune, lifeguard, Aquatics.
Nine employees left employment with GRF in July: Diane Della Rosa, Receptionist, Executive Services; Susan Wallace, purchasing agent, MOD Administration; Holden Ganch, range worker, Golf Pro Shop; Keith Peedle, carpenter, Building Maintenance; David Bondar, lifeguard, Aquatics; Marla Pascoe, HR generalist, Human Resources; Jeff Barberio, equipment operator l, Golf Course Operation; and William Kim, Board Services coordinator, Mutuals’ Board Office.